To main content

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

During a survey campaign in 2006 initiated by the owners of the East Java Gas Pipeline, PT. Pertamina Gas and PT. Trans Javagas Pipeline, a large number of critical spans were identified, many of which above the threshold for vortex induced vibrations. Boskalis Offshore, through its Indonesian entity PT. Boskalis International Indonesia, was contracted to rectify 799 critical spans by means of installing a total of 804 rock berms. These berms reduce span lengths and prevent that the critical span length will be exceeded within the remaining lifetime of the pipeline.

Support Berm Installation 

For the support berm installation works Boskalis deployed its dynamically positioned fallpipe vessel (DPFV) Seahorse. This vessel, with a carrying capacity of 18,000 tons of rock, is able to position its fallpipe directly above the live pipeline, meanwhile ensuring sufficient vertical clearance to compensate for current and swell. The DP Class II capabilities of the vessel allow for accurate dumping with a minimum of losses resulting in a short project execution time. One load of 1-5' rock was brought from Norway and additional loads were loaded in Indonesia. Rock was supplied by a quarry operating in the inlands of East Java, delivering rock via the road to a temporary stockpile at the port of Paiton. During loading the 1-5' rock was transported by truck from the temporary stockpile to the feeder and via a conveyor belt into the holds of the DPFV Seahorse. The entire temporary supply chain for rock supply, from quarry to Seahorse, was purposely set up for the execution of this project. Prior to commencement of the rock dumping operations, a pre-survey was carried out by Seahorse's ROV, equipped with multibeam echosounders. This survey was used to identify the start and end points of the free spans. Subsequently, the design per span location was prepared and the berms were installed. A post-survey was carried out to ensure that the berms were installed as specified. When the results of the post-survey were satisfactory, the vessel moved to the next position.

Related projects

Selected filters
Beach_pull_at_Pulau_Pemping2_header.jpg

Seabed preparations, PGN

The pipeline between Pulau Pemping, Indonesia, and Pulau Sakra, Singapore, is the final link of the transportation system for natural gas from onshore fields on South Sumatra to Singapore. The successful completion of the Engineering, Procurement and Construction contracts for the 27-kilometers 28-inch gas pipeline with a 96-core fibre optic cable in one of the busiest ports and shipping traffic zones of the world marked a milestone for Boskalis. The scope of work comprised not only seabed preparations and protective rock berm installation - Boskalis Offshore core activities - but also pipeline manufacturing and installation.

111-1126_IMG_header.jpg

Deepening of the Eems-pipeline

The 42" Eems pipeline is part of the pipeline connection between the gas cleaning and drying plant of Phillips Petroleum at Rysumer Nacken in Germany, and the natural gas pipeline network in the Netherlands. The gas is obtained from the Ekofisk gas field in the Norwegian region of the North Sea. The pipeline crosses the morphologically dynamic Eems estuary over a length of 4 km, passing both the deep shipping lane ‘Oostfriesche Gaatje’ and the shallow sand bank ‘Paap’.

Development gas export pipeline,
Hibiscus to Point Fortin

The NCMA Development Project comprised the development of the North Coast Marine Area, which is located in the Caribbean Sea and Bay of Paria, Trinidad. The project included the installation of a 24" Gas Export Pipeline from the Hibiscus Platform to a landfall at Point Fortin. From the landfall the pipeline was routed by directional drilling and by surface laid pipeline, to a termination point in the Atlantic LNG Terminal at Point Fortin. As part of this project Boskalis was awarded the contract for the provision of landfall, directional drilling and onshore pipeline installation and testing of the 24" gas pipeline system.

Sandpiper_foto_offshore_2_header.jpg

Hanze F2a Development Project

Hanze, 200 kilometers offshore Den Helder in block F/2 of the North Sea, is the first operated development in the Dutch sector by Germany's Veba Oil. The oilfield reserved approximate 34 million bbl, plus 40 bcf of associated gas. 

Installation gas pipeline, Takoradi

Late November 1998 Boskalis was awarded a subcontract for the installation of two marine pipelines to supply and discharge cooling seawater for the Takoradi thermal power plant that was under construction for the Volta River Authority, near the village of Aboadze approximately 20 kilometers north-east of Takoradi, Republic of Ghana.

WD_Fairway_and_Sandpiper_near_platform_header.jpg

Re-insulation Gannet 'C' Bundles, North Sea

The Gannet 'C' satellite field, which is located in the North Sea at 112 miles East of Aberdeen in 95-meter water depth, comprises four drill centres, each having one or more producing wells. The drill centres are connected to the local platform Gannet 'A' by four flowline bundles with a total length of 10 kilometers. A glycol-based gel, filling the annulus of the Gannet 'C' carrier pipe, insulated the individual flow lines. Prompted by degradation of the gel and the resulting drop in oil and gas arrival temperatures at the platform, an EPIC project took off for a re-insulation system. The objective of the re-insulation system was that it should provide sufficient insulation to the bundles in order to safeguard production during the total field life of Gannet 'C', being a minimum lifetime of 15 years. Boskalis Offshore was supported by Hydronamic - the in-house engineering department.