Port and MOF, LNG plant Barrow Island, Gorgon

Design and construction of a new port and materials offloading facility in a class 'A' nature reserve. The project owner is developing LNG process facilities on Barrow Island off the north west coast of Western Australia approximately 140 km west of Dampier and 95 km north east of Onslow. Barrow Island is a Class A Nature Reserve and an internationally important conservation estate.

Scope of work

Boskalis’ scope of work on the project included:
  • Detailed design and construction of a Pioneer Materials Offloading Facility (PMOF).
  • Design and construction of abutment structures for a Ro-Ro berth, module carrier berth and barge berth.
  • Design and construction of mooring dolphins and access walkways for the PMOF barge berth, module carrier berth and Ro-Ro berth.
  • Dredging and reclamation work for the approach channel, turning basin and berth pockets associated with the construction of the MOF.
  • Dredging for the LNG jetty area including an approach channel, turning basin and berth pockets.
  • Installation of temporary and permanent navigation aids including two permanent front and rear lead support structures.
  • Provision and operation of a Marine Construction Support Vessel to accommodate personnel involved in the Project.
  • Construction of the Eastern Materials Offloading Facility (EMOF) causeway including all armour rock, construction of a breakwater, placement of X-blocs and installation of concrete nib wall.
  • Compaction of the EMOF (Cofra).
  • Materials testing (Boskalis Environmental).

Dredging and reclamation works

The dredging works consisted of 2 major parts:
  • A MOF access channel and turning basin to create access for heavy load transport vessels to bring in construction materials and large modules for the construction of the LNG plant on Barrow Island.
  • An access channel and turning basin for the LNG carriers once the plant is operational.

Rock protection and breakwater works

These works consisted of 3 major components:
  • Design and construction of a protection of the MOF platform against cyclonic waves with rock only.
  • Construction of a protection of the EMOF platform against cyclonic waves with rock underlayers and concrete X-blocs.
  • Construction of a breakwater for protection of a tug harbour against cyclonic waves with rock underlayers and concrete X-blocs.

Related projects

Selected filters

Installation gas pipeline, Gelugor Mainline

The Gelugor transportation system is a 24'' gas pipeline from the Tenaga Nasional Berhad (TNB) Prai Power Station, Mainland Peninsular Malaysia across the Strait of Pinang to the TNB Gelugor Meter Station on Pinang island. The pipeline has a length of 6.4 km and was put into use in the beginning of 2000. Boskalis Offshore has constructed the protection of the pipeline with rock material. The function of the protection differs along the chainage of the pipeline. A shipping channel is situated between the island and the peninsular. The pipeline in the shipping channel has been covered for to protect against ship anchors (drop and drag).

Rosario_001_header.jpg

Fixed Link between Rosario and Victoria

The Joint Venture Boskalis International - Ballast Nedam JV was a subcontractor to the Consorcio Impregilo, Hochtief, Roggio and Techint which was awarded the construction of the fixed link between Rosario, in the province of Santa Fe and Victoria, in the province of Entre Rios. The Client in this project was the Argentine Government, and the leader of the Consorcio was Impregilo. The Consorciol executed all the civil constructions such as bridges while the JV Boskalis International – Ballast Nedam (BKI/BND) constructed, using sand only, the road embankments, connecting the several bridges.

DSC03484_header.jpg

Cleanup, Westergasfabriek

The Westergasfabriek was built by the British firm Imperial Continental Gas Association (ICGA) in 1883, and was at the time the biggest coal-fired gas factory in Amsterdam. The project site, covering four hectares, housed coal storage yards, gasometers, purification plants, a water tower and office buildings, all designed by the famous Dutch architect Isaac Gosschalk. The municipal energy company used the site for storage into the early 1990s.

Bahrain_header.jpg

Land reclamation, Shaikh Khalifa Bin Salman Causeway

The Shaikh Khalifa Bin Salman Causeway is located in the State of Bahrain in an expanse of water called the Khawr Al Qulayah. It connects the Hidd Drydock Highway to the Mina Sulman Port. This major infrastructure project is carried out in advance of the planned expansion of the Bahrain port activities. This New Port project is planned at the Hidd side and via the Shaikh Khalifa Bin Salman Causeway direct connected with the existing Mina Sulman port and Saudi Arabia. The total length of the Shaikh Khalifa Bin Salman Causeway is approximately 6,500 m, including a bridge of 400 m, which was constructed in 2000.

Oresund.jpg

Tunnel construction Øresund, Denmark - Sweden

The Øresund Tunnel forms part of the Øresund Link that connects the cities of Copenhagen in Denmark and Malmö in Sweden across the Øresund.

Chek_Lap_Kok__09-06-1995.jpg

Land reclamation Check Lap Kok airport Hong Kong

In 1996 Hong Kong was a modern city-state with almost 6 million inhabitants where air traffic was a very important component for economic activity. The old airport Kai Tak, with a single runway, was no longer able to cope with the growing number of passengers and amount of freight.  The authorities decided to build a new, bigger airport at a new location in Hong Kong, a 350 hectares hilly island off the coast about 28 km west of the city center.