To main content

Rock installation, PDET

In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

The pipeline network total extension of 25 km consists of three Pipeline End Manifolds (PLEM) installed on the seabed at a depth of approximately 100 m. The terminal, constructed to comply with the Oil Outflow and Handling Master Plan of Campos Basin – PDET, was the solution for the oil outflow produced at platforms P51, P53, P55 and Roncador module. Petrobras pro-actively initiated this project to ensure the future integrity and safety of the oil production facilities. Petrobras considered specialized accurate rock installation techniques to protect, stabilize and isolate the pipelines and subsea structures and in doing so to protect the environment. For Petrobras, Boskalis and partners it was the first time an IBAMA (Environmental) licensed rock installation project was carried out in Brazil. IBAMA issued this license after a detailed analysis of amongst others the impact on the environment and the proposed measures to mitigate turbidity during the installation process. Also the IBAMA guidelines with regard to the selection of the quarry mining, production of the rock, logistics and actual loading of the vessel, were fully met.

Quality and safety performance

The safety performance on the project was excellent. Before mobilization several safety and quality pre-inspections were carried out by independent auditors and Petrobras representatives; all findings and observations were resolved before arrival in Brazil to guarantee a smooth importation process. During the project preparation phase the Boskalis NINA (No Injuries No Accidents) program was implemented; all truck drivers and other personnel were successfully trained and explained the values and rules of the safety program. Special attention was paid to safe driving, the Boskalis Offshore theme for the year 2011. Thanks to the thorough preparations almost 400,000 accident-free km were driven on the project.

Related projects

Selected filters
quarry.jpg

Pipeline survey and freespan correction, Bach Ho

The Bach Ho Gas Pipeline is located at the South Coast of Vietnam in the province of Vung Tau and comprises a 16" pipeline installed in 1994. The 16" pipeline is one of the main production lines of Petrovietnam Gas Company (PVGAS) and important for the supply of natural gas to electrical power plants, production and export of LPG and other domestic users.

Gas pipeline project, Trans Thailand Malaysia

The Trans Thailand Malaysia Gas Pipeline Project comprised the installation of a 34 inch concrete coated gas pipeline, running from the joint Thai-Malaysia development area approximately 270 kilometers offshore towards the southern Thai coast near Chana. As part of this project a contract was awarded to the Boskalis Offshore B.V. - Tideway B.V. consortium for the provision of the dredging and backfilling works, whereas Boskalis Offshore provided the main equipment and project support.

Taurus___BKM100_header.jpg

Shore approach and landfall works, Libyan gas transmission system

West Libya aimed to enhance its position in the supply of continental Europe's energy needs. As the demand for cleaner energy was rising and gas consumption in Italy wasexpected to increase, Libya and Italy found common ground for cooperation. Construction of a 700 million USD gas treatment plant in Mellitah was the centrepiece of this West Libya gas project. The Mellitah plant is supplied with gas from the desert Wafa field, 520 kilometers south-west of Tripoli, and from the offshore Bahr Essalam field, 110 kilometers north of Tripoli.

Seahorse_04_header.jpg

Glory hole excavation, White Rose

The White Rose offshore oil field is the third major oil field in the Jeanne d’Arc Basin on the Grand Banks, some 350 kilometers east of St. John’s, Newfoundland, Canada and within 50 kilometers from the Terra Nova and Hibernia fields. The South White Rose oil pool covers approximately 40 square kilometers and contains an estimated 200-250 million barrels of recoverable oil.

Woodside_3_header.jpg

Dredging and backfilling, TSEP

In order to increase the production capacity from the gas condensate fields located off the North West Coast of Western Australia, Woodside Energy Limited, on behalf of the North West Shelf JV Participants, has realized the installation of a multiphase subsea 42" pipeline. The new trunkline supplements an existing 40" pipeline, which conveys gas/condensate from the North West Shelf fields - North Rankin, Goodwyn and Cossack/Wanaea - to onshore treatment facilities located on the Burrup Peninsula near Dampier, Western Australia.

Beach_pull_at_Pulau_Pemping2_header.jpg

Seabed preparations, PGN

The pipeline between Pulau Pemping, Indonesia, and Pulau Sakra, Singapore, is the final link of the transportation system for natural gas from onshore fields on South Sumatra to Singapore. The successful completion of the Engineering, Procurement and Construction contracts for the 27-kilometers 28-inch gas pipeline with a 96-core fibre optic cable in one of the busiest ports and shipping traffic zones of the world marked a milestone for Boskalis. The scope of work comprised not only seabed preparations and protective rock berm installation - Boskalis Offshore core activities - but also pipeline manufacturing and installation.