To main content

1915 Çanakkale Bridge

The 1915 Çanakkale Bridge, also known as the Çanakkale Strait Bridge, is a proposed suspension bridge being constructed in the Çanakkale area in Turkey. Situated just south of the towns of Lapseki in Asia and Sütlüce Village in Europe. The bridge will span the Dardanelles strait, about 10 km south of the Sea of Marmara.

The bridge is the centerpiece of the 324 km long Kınalı-Balıkesir Motorway, which will connect the O-3 and O-7 motorways in East Thrace to the O-5 motorway in Anatolia. With a main span of 2,023 m, the bridge will become the longest suspension bridge in the world.

The total length of the bridge will be 3,563 m and together the approach viaducts the length reaches 4,608 m. The total height of the bridge’s two towers will be 318 m tall. The deck of the bridge will be at 72.8 m hight and have a total width of 45.06 m and a maximum thickness of 3.5 m. The deck will carry six lanes (three in each direction) of motorway, together with two walkways on each side for maintenance.

On January 26, 2017, a Joint-Venture SK Engineering & Construction Co., Daelim Industrial Co., Limak Insaat Sanayi ve Ticaret AS and Yapi Merkezi Insaat Sanayi ve Ticaret AS was appointed as contractor for the construction of the bridge.

On March 18, 2017, the groundbreaking ceremony was held, marking the commencement of the construction works. Construction activities are underway and scheduled to be completed by March 2022.

Boskalis Offshore Marine Services was contracted to execute a part of the lifting operations ,a float-over scope to install the tie-beam and deliver a part of the vessels for transport and installation of the foundation caissons.

Related projects

Selected filters

Installation gas pipeline, Balgzand-Bacton

BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m3 of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.