Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

The consortium comprising Boskalis, Van Oord, NMDC (Abu Dhabi) and Jan de Nul (Belgium) had the task of dredging the 35 km long New Suez Canal parallel to the existing canal. This involved dredging a record breaking 200 million m3 of sand, clay and rock in less than 9 months. In addition, two Service Channels (80 m wide and design depth -10 m CD) and two Cross Channels (50 m wide and design depth of -6 m CD) were dredged to connect the existing canal and the New Suez Canal.

Enormous scale

Dredging 200 million m3 of material in a period of 9 months required the deployment of the world’s largest dredging fleet comprising 21 Cutter Suction Dredgers, 5 Trailing Suction Hopper Dredgers and 2 Water Injection Dredgers. The dredging vessels cut the capital volume and pumped the mixture of soil and water into 16 disposal basins totaling an area of 73 million m2. This required a total length of 85 km floating and shore pipeline.

Complex planning

To ensure the project was completed on time, the fleet of vessels had to be managed to achieve optimum production levels. The first planning task was to enable as many vessels as possible to dredge simultaneously. This required breaking in at both ends of the New Suez Canal and at four points along the existing canal to create ten fronts for the dredging vessels at an early stage in the project.

Logistics

The project was a major challenge in logistics and could have been a project on its own on managing the logistics of incoming shipments arriving on their own keel, by semi-submersible vessels, cargo vessels, and regular air freight, sea freight and road transport.

Time pressure

The main challenge for the Consortium was the time frame in which all dredging had to be completed. A project of this scale was initially estimated to take three years to complete, but the President of Egypt had set the limit for completion at one year. The period from tender to contract award was only one month, and dredging started within a month. The New Suez Canal was open for shipping in just five days after completion of the dredging works.

Facts and figures

  • 35 km long canal with bottom width 147 to 177 m and design depth -24 m CD
  • 2 Service Channels (width 80 m and design depth -10 m CD), and 2 Cross Channels (width 50 m and design depth -6 m CD)
  • 9 months execution period including preparations
  • 28 dredgers on site including 21 Cutter Suction Dredgers, 5 Trailing Suction Hopper Dredgers and 2 Water Injection Dredgers
  • 85 km soil conveying pipeline (floating and shore pipeline)
  • 16 disposal basins located on the east and west banks of the New Suez Canal
  • Approximately 2,000 people from 45 countries employed on site; over 4.5 million man-hours, over 3,700 project safety inductions, and no fatal injuries or permanent disabilities
  • The New Suez Canal was opened for shipping on 6 August 2015, 5 days after completion of dredging
  • Extension of time was not possible

Related projects

Selected filters
DSC04359_header.jpg

Port access channel dredging, Walvis Bay

The port of Walvis Bay is a naturally sheltered deepwater harbor on the west coast of Africa. The port is part of a transit route linking Southern Africa, Europe and the Americas and it is Namibia’s largest commercial port, handling around 5 million tons of cargo each year. The container terminal can accommodate a throughput of about 250,000 containers per year.

IMG_8772_header.jpg

Coastal protection, St. Petersburg

St. Petersburg is a UNESCO World Heritage City, but its location along the River Neva means that it has been threatened by over 300 floods since its founding by Peter the Great in 1703. The completion of the new 25 km long storm-surge barrier across the Gulf of Finland ensures that the city will no longer be vulnerable to high tides and devastating floods. As a result of the new Flood Protection Barrier, however, the old winding access channel had to be replaced with a new, straighter, more easily navigable channel.

Delflandse_coast___3__header.jpg

Coastal protection, Delfland coast

In August 2008 Van Oord and Royal Boskalis Westminster N.V. have been awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce a weak link in the Delflandse coast . The contract is worth EUR 120 million of which Van Oord and Boskalis have an equal share.

IMG_1888_header.jpg

Cleanup, Zellingwijk area

The Zellingwijk quarter of the village of Gouderak was built in the middle of the last century. In the early 1980s it became clear that the soil underneath this residential area was heavily contaminated as a result of the dumping of waste - mainly mineral oils and pesticides. The homes built on the site were subsequently demolished in the mid-1980s. Pending definitive remediation work, a layer of concrete / asphalt was applied to seal the site.

DSCF0279_header.jpg

Overview activities, Bahrain

The Kingdom of Bahrain is an island located in the Gulf, east of Saudi Arabia and north of Qatar and connected with its neighbour Saudi Arabia since the year 1980 with a 25 km long causeway. The archipelago consists of some 30 islands with a total of 160 km of shoreline and has a population of 800,000. Whereas the surface of Bahrain in the year 1960 was around 650 km2, the last decennia have seen a steady increase in the surface till a respectable figure of 740 km2 in 2007. This increase has been achieved by a various number of small and mayor reclamation projects.

37ac96e429c252fd55f1136ce6374c9e_image_header.jpg

Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.