To main content

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.

SCOPE OF WORK

  • Mobilisation of cable repair vessel and auxiliary equipment
  • Mobilise cable storage pan and turntable onto transpooling barge
  • Load spare cable from the storage pan onto the Ndurance
  • Determine cable cut position along cable route
  • Cut, test and seal operations
  • Removal of sea end cable till jointing location
  • Cut cable and joint to new cable section
  • Lay down joint No.1 on sea bottom and lay new section of cable
  • Recover shore end and joint both cable ends
  • Lay down joint No.2 and omega on sea bottom
  • Post lay ROV survey

Having signed a Power Cable Maintenance Agreement (PCMA) in the summer of 2012, Boskalis maintains a long standing relationship with Channel Islands Electricity Grid (CIEG). The parties involved in the agreement have worked together to achieve a quick response method for maintaining and where necessary repairing the subsea assets that are so vital for the islands communities.

In November 2014 Boskalis was instructed to mobilise for a preemptive repair after CIEG had detected a potential vulnerability in the subsea cable, which provides a power link to the Island.

Extensive and detailed engineering was carried out over the Christmas and New Year period, owing to the very difficult repair area.

The large tide range and strong, unpredictable currents around the shallow rocky outcrops of Havelet Bay created a number challenges during the engineering phase. Being a winter repair in the English Channel the planning for the project was critical. Mobilisation of the CLV “Ndurance” started on the 12th January with the cable being loaded from the Boskalis storage only 5 days later. The vessel arrived in Havelet bay, Guernsey on the 21st January to start the repair operations after 48 hours of DP familiarisation along the challenging route. The repair operation was broken into sections to ensure that each operation could be complete once it had been committed to. The repair was completed on schedule and to the satisfaction of all parties on the 5th February 2015.

Guernsey Electricity issued a statement which commended the professionalism and efficiency of Boskalis throughout what was a challenging repair in a difficult period.

Related projects

Selected filters
FF66817_header.jpg

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Cornelis_Zanen.jpg

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Gabon_Libreville1920.jpg

Port development,
Libreville - Gabon

A new area was constructed in the Port of Libreville for a mineral terminal, dry dock, fishing port, processing facilities and other port activities, such as aggregate processing. This new port development was required to improve and strengthen the logistic capacity for the inland mining industry, to reduce export costs, and thus to increase the competitiveness of mineral exports from Gabon.

Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

IMG_3549_header.jpg

Cleanup sediment treatment, Fox river

As a result of industrialization the riverbed of the Fox River (Wisconsin, USA) had become contaminated with PCBs (polychlorinated biphenyls). Joining together a number of large paper mills based on the banks of the river have established the Fox River Cleanup Group to handle the remediation project. The site is on the federal Superfund program’s National Priorities List.

Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.