Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.

SCOPE OF WORK

  • Mobilisation of cable repair vessel and auxiliary equipment
  • Mobilise cable storage pan and turntable onto transpooling barge
  • Load spare cable from the storage pan onto the Ndurance
  • Determine cable cut position along cable route
  • Cut, test and seal operations
  • Removal of sea end cable till jointing location
  • Cut cable and joint to new cable section
  • Lay down joint No.1 on sea bottom and lay new section of cable
  • Recover shore end and joint both cable ends
  • Lay down joint No.2 and omega on sea bottom
  • Post lay ROV survey

Having signed a Power Cable Maintenance Agreement (PCMA) in the summer of 2012, Boskalis maintains a long standing relationship with Channel Islands Electricity Grid (CIEG). The parties involved in the agreement have worked together to achieve a quick response method for maintaining and where necessary repairing the subsea assets that are so vital for the islands communities.

In November 2014 Boskalis was instructed to mobilise for a preemptive repair after CIEG had detected a potential vulnerability in the subsea cable, which provides a power link to the Island.

Extensive and detailed engineering was carried out over the Christmas and New Year period, owing to the very difficult repair area.

The large tide range and strong, unpredictable currents around the shallow rocky outcrops of Havelet Bay created a number challenges during the engineering phase. Being a winter repair in the English Channel the planning for the project was critical. Mobilisation of the CLV “Ndurance” started on the 12th January with the cable being loaded from the Boskalis storage only 5 days later. The vessel arrived in Havelet bay, Guernsey on the 21st January to start the repair operations after 48 hours of DP familiarisation along the challenging route. The repair operation was broken into sections to ensure that each operation could be complete once it had been committed to. The repair was completed on schedule and to the satisfaction of all parties on the 5th February 2015.

Guernsey Electricity issued a statement which commended the professionalism and efficiency of Boskalis throughout what was a challenging repair in a difficult period.

Related projects

Selected filters
Marker_Wadden_spread_def_1920.jpg

Construction of
Marker Wadden

Boskalis has been awarded the first phase of the Marker Wadden development in the Netherlands. The project includes the construction of an island with underwater landscaping. The Marker Wadden are natural islands that will be developed in the Markermeer lake in the years to come. They will provide a major boost for the ecological quality of the Markermeer lake. The natural shores of the islands will give fish more opportunities to spawn and feed. As a result, large numbers of birds such as terns and waders will return to the area because there will be more food for them. The construction of the Marker Wadden will transform the map of the Netherlands.

Adelaide.png

Outer harbor channel widening, Adelaide.

The Port of Adelaide is the primary port in South Australia, located at Outer Harbor. The port is operated by Flinders Ports Pty Ltd (Flinders Ports) and handles both container and cruise vessels, contributing significantly to the State’s economic activity. Flinders Ports identified the need for an upgrade of the existing infrastructure driven by the emergence of Post Panamax class vessels. To meet this growth the existing channel had to be widened to accommodate vessels with a maximum width of 49 m without operational restrictions. Flinders Ports contracted Boskalis to execute the dredging works.

Medium-FF95893.jpg

Johan Sverdrup, transport.

Samsung Heavy Industries Co., Ltd. is Equinor’s Fabrication and Transport contractor of the Johan Sverdrup project. Boskalis has been awarded by Samsung as transportation contractor for this project.

DSC_0204_header.jpg

IJsseldelta

The IJsseldelta project is part of the national Room for the River program, which comprises over 30 measures aimed at upgrading the flood defenses in the Dutch river areas. The project involves lowering the summer bed of the Lower IJssel river along a length of 7.5 kilometers near the town of Kampen and creating a bypass to the south of Kampen.

Port expansion, Tuas Mega Port Singapore

Boskalis is part of a consortium that won a contract related to the construction of the Tuas Mega Port in Singapore. After Shanghai, Singapore is not only the world's largest container port, it also handles 50% of global crude oil production and it is the planet's busiest transit port. The port is the economic motor of Singapore, which is constantly struggling with a shortage of land.

DJI_0005__4_.JPG

Construction of greenfield port and breakwater for Dangote quays Lekki

The Dangote Group, owned by Aliko Dangote, is building Africa’s largest oil refinery and fertilizer plant in Lekki, 60 kilometers east of Lagos, Nigeria. To facilitate the import of out-of-gauge components and other materials required for construction activities, a port was constructed