A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Because the Hondsbossche and Pettemer Sea Defense no longer meets safety standards Boskalis is to replenish the coastline using sand. A daring design has been made in which safety is paramount but added value for the environment is also an important aspect: not just safe but also attractive and offering something for everyone. The middle section will provide space for nature while at either end, near the villages of Camperduin and Petten, the focus is on added value for recreation.

The contract

A joint venture of Boskalis Nederland and Van Oord has won a contract from the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin. The client had stipulated 'a safe design using sand with added value for nature and recreation'. Boskalis won the contract on the strength of its unique design ideas. The contract comprises the construction of the new sandy coastline and its maintenance for the next 20 years. The commissioning body for the maintenance part of the contract is the Dutch department of public works. The project, part of the second national Flood Protection Program, involves creating beaches and dunes through sand replenishment.

Work

This weak link in the sea defense will be strengthened using 35 million m3 of sand from the sea, to be supplied by five trailing suction hopper dredgers: three for foreshore replenishment and two for beach replenishment. Coordination between the two large vessels has been arranged in such a way that they can unload simultaneously; the fact that the vessels do not have to wait for one another means lower fuel consumption and therefore lower carbon emissions. Replenishment of the foreshore has been going on since March 2014, with large quantities of sand having been dumped and rainbowed just off the coast. Beach replenishment work started in July and involves pumping the sand for the new beach and dunes through a 1.5 kilometers long underwater pipe. To prevent drifting the new dune will be planted with beach grass and will feature dips in the lee of the wind to allow drift sand to settle on the dune. Conversely, where drifting is desirable we are doing our best to allow for this as well.

Planning schedule

The design was announced in December 2013 and execution of the project started in early 2014. The safety of our coastline must be back up to standard by 31 December 2015. After the sand is in place the joint venture will still be busy in early 2016 realizing cycle tracks, footpaths and bridleways, and creating beach access points as well as several unique features such as the panoramic dune and the beach lagoon. After completion the joint venture of Van Oord and Boskalis Nederland will be responsible for the maintenance for a period of 20 years.

Related projects

Selected filters
IMG_0064_header.jpg

Port development, Gothenburg

Gothenburg turns around some 34 million tons of cargo annually, including 700,000 TEU (containers), and is unique in the region. With regard to the variety and frequency of calls from intercontinental liner trade the port is outstanding in Sweden. The port can be reached from the sea via two different channels: Torshamnen Fairway and Böttö Fairway. From a navigational point of view both channels needed to be deepened and widened at a number of places. Thus there were two good reasons to enhance the fairways: securing the port’s future as the premier port for liner trade and creating safer navigation. This resulted into a major dredging contract which was awarded in June 2002 to Boskalis Westminster Dredging Company.

03_header.jpg

Remediation, Urk harbor area

Many port areas requiring dredging works have been forced to put projects on hold due to the absence of an environmentally safe solution for the disposal or processing of contaminated sediments. While this is a global problem, the availability of central, large-scale repositories in the Netherlands has transformed disposal economics at the national level. Nevertheless, the high level of debris encountered during the dredging of ports and harbors remains a major challenge to all contractors. The hydraulic transport of sediments with a high debris content is impossible.

Pusan_New_Port_5_header.jpg

Port construction, Pusan

The 4th largest container terminal in the world is located in the South East of the South Korean peninsula at Busan. As the old port is completely surrounded by the metro-city, expansion of the old port is restricted. To solve the chronic phenomenon of cargo congestion MOMAF (Ministry of Marine and Fisheries) decided in 1997 to construct a new port situated 20 km west of Busan with a final total handling capacity of 4.6 million TEU and total expenses of 4.2 billion USD.

mejillones_5_header.jpg

Port construction and environmental monitoring, Mejillones

Boskalis International B.V. was working as a subcontractor to the Chilean civil contractor Empresa Constructora BELFI SA, which was awarded the contract to construct phase 1 of the New Mega Port Mejillones. This port has been developed in order to ship the copper of the Chilean mining corporation CODELCO.

Luchtfoto_milieubrochure_header.jpg

Cleanup, Ketelmeer

Ketelmeer, a lake in the Netherlands with a length of some 10 kilometers and a width varying from two to three kilometers, separates the North Eastern and Southern Polders constructed during the late 1960s and early 1970s. It is a major example of the problem of 'historic pollution'. Lake Ketelmeer receives the waters of the Rijn and IJssel and over a period of three or more decades, tens of millions of cubic meters of highly contaminated sediments entered Ketelmeer from hundreds of upstream locations. The bottom was covered by polluted sediments to an average depth of 50 cm. A significant proportion of this material had to be removed, or capped by the cleaner sediments of recent years, if a normal aquatic environment was to be restored.

Warnow_Tunnel__3__header.jpg

Tunnel construction Warnow, Rostock

The Warnow Tunnel is located in Rostock, Germany, at the old mouth of the river Warnow in the Baltic Sea. In the DDR period this area grew out to be the main harbor of East-Germany. After the 'turn' (die Wende) in 1989 the port more or less died. Goods came cheaper and quicker from Rotterdam, Bremen and Hamburg by rail.