To main content

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

The project consists of the following distinctive elements:

  • Dredging of access channel and turning basin;
  • Ordnance removal;
  • Rock works for breakwater and groyne construction;
  • Civil works for breakwater and groyne construction.

Dredging works

An access channel and turning basin were dredged to a depth of -14.50m. Dredging started in August 2011 and was completed by January 2013, with a total volume of 8.2 million m3 sand being removed by the Trailing Suction Hopper Dredgers (TSHD) Crestway, Shoreway, Shoalway and Barent Zanen.

Related projects

Selected filters
P67.jpg

P67 FPSO Transportation

On behalf of Company Petrobras and Client COOEC, Boskalis executed the dry transportation of the P-67 FPSO in 2018 from the COOEC Qingdao yard in China to Rio de Janeiro in Brazil. The P-67 FPSO will produce 150,000 bpd and compress six million cubic meters of natural gas daily in the Lula North section of the Lula-Cernambi field in the Santos basin.

Pluit_City_Island-bird_eye_view.jpg

Artificial island
off the coast of
Jakarta, Indonesia

Boskalis has been awarded a contract by PT Muara Wisesa Samudra to design and construct an artificial island measuring 160 hectares off the coast of Jakarta, Indonesia. The work is part of the dredging and land development works for the new Pluit City. It will be executed in a joint venture with Van Oord.

Harderwijk_Lorentzhaven__7__header.jpg

Redevelopment Waterfront, Harderwijk

Boskalis Nederland is involved in one of the largest redevelopment projects in the Netherlands. The Harderwijk Waterfront project involves the complete transformation of the lakeside area of this IJsselmeer town. The project covers a strip approximately six kilometers long, combining homes, work and recreation in a natural way. The Harderwijk Waterfront will generate a quality boost in many areas: quality of life, employment, traffic, tourism and the environment.

Medium-Foto_1_-_artist_impression_nw_situatie_A1_afslag_met_spoorbrug__1_.jpg

Road enlargement motorway A1-A6, Diemen-Almere

The A1/A6 project is one of the five sub-projects for Rijkswaterstaat that are included in the upgrading of the road network linking Schiphol Airport, Amsterdam, and Almere (SAA). The total length of the SAA link is 40 kilometers. Boskalis, together with partners, is responsible for the section from the Diemen intersection to Almere, a distance of approximately 23 kilometers.

29-8-11_006_header.jpg

Port maintenance,
Açu Port

Açu Port in São João da Barra, Rio de Janeiro (Brazil) is one of the largest port-industry complex in Latin America. The port consists of two terminals: T1, an offshore terminal for handling iron ore and oil, and T2, an onshore terminal built around the inner navigation channel which accommodates offshore supply companies and will handle bauxite, general cargo and vehicles.

Shell Malikai

Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell Petroleum Company is the designated Operator. A floating Dry Tree Unit (DTU) will be installed over Malikai field utilizing a Tension Leg Platform (TLP) design that suits the Malikai environment.