Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

The original Boskalis Dredeco Joint Venture contract with NCIG was to dredge in preparation for Coal Export Terminal 3, with a capacity of 30 Mtpa. Material  from the South Arm of the Hunter River would be removed to create two berth pockets (Kooragang K8 and K9). During execution of this Main Contract, however, additional works were added:

  • The dredging to the west side of the K9 area to provide sufficient depth along the future K10 Berth Pocket for future wharf construction (this is part of the NCIG stage 2 works for 45 Mtpa);
  • The precision environmental dredging of clean and contaminated materials in a Heavy Lift vessel Channel (HCL) and in the so-called Secondary Remediation Zone (SRZ) under a separate contract agreement;
  • Dredging to the required depth for the Port Waratah Coals Services (PWCS) Kooragang K7 Berth Pocket and basin, combined with the NCIG Temporary Coal Shipping Channel (TCSC), which was executed as a variation under the scope of the original Main Works contract.

Related projects

Selected filters
CIMG1866_header.jpg

Coastline fixation, Cotonou

The project was developed to arrest coastline erosion in the densely-populated centre of Cotonou caused by two phenomena: erosion and human interference along the West African coastline.

gavle_hamn_201319_DD_Bewerkt_header.jpg

Port extension, Port of Gävle

The Port of Gävle is located on the east coast of Sweden in the Gulf of Bothnia, facilitating Swedish imports and exports. The client wished to improve maritime safety and accessibility, and to increase the throughput of goods in this harbor.

20120229-DSC_3214_header.jpg

Port expansion, Onne

In May 2011 Boskalis was awarded the project for the expansion of the Federal Lighter Terminal and Federal Ocean Terminal of the Onne Port Complex by Prodeco International Limited. The project entails the reclamation of approximately 200 ha with suitable materials from nearby borrow areas.

Boskalis_Genova_VOLO_ph-merlo_110112-3725_header.jpg

Port upgrade, Genoa

The deepening and extension of the port of Genoa is needed to accommodate the larger container vessels and the ferries of MSC. The client is the Port Authority of Genoa. The project is being executed by Boskalis Italia S.r.l. in a joint venture with Tecnis S.p.A., an Italian company that is responsible for the construction work.

B_nieuw_header.jpg

Port and MOF, LNG plant Barrow Island, Gorgon

Design and construction of a new port and materials offloading facility in a class 'A' nature reserve. The project owner is developing LNG process facilities on Barrow Island off the north west coast of Western Australia approximately 140 km west of Dampier and 95 km north east of Onslow. Barrow Island is a Class A Nature Reserve and an internationally important conservation estate.

DSC_5770_header.jpg

Port development, Mombasa

The Port of Mombasa is currently the biggest port on the coast of East Africa north of Durban, and the only international port in Kenya. It is now in the throes of a huge expansion drive to both increase cargo handling capacity and accommodate Panamax and Post Panamax vessels. The port is a transit route for, mainly, Uganda, Rwanda, South Sudan and Northern Tanzania. The current container terminal has an installed capacity of 250,000 TEU but handled more than 770,000 TEU in 2011. The port will raise its profile as a regional hub by building a second container terminal with a capacity of 1.2 million TEU. The port authority decided to construct the container terminal in phases.