To main content

Dredging, reclamation and
shore protection, Soyo LNG

Angola is one of the world’s deep water oil exploration ‘hot spots’. More than 50 significant oil discoveries in Blocks 14, 15, 17 and 18 are believed to contain at least 10 billion barrels of oil. With the increase in oil production comes large quantities of associated gas. Historically, in the absence of a local market, associated gas has been flared or reinjected into the reservoirs. Sonangol, the state oil company, and some of its oil producing partners developed the Angola LNG Project to reduce flaring of gas and curtail gas injection. Angola LNG is a joint venture project involving the major oil producers in the country. Sonangol and Chevron are the co-leaders of the project; the other partners are Total, ENI and BP.

The LNG plant will be built on a site south of the Congo River, in Zaire Province, West of the city of Soyo. The plant will have a capacity of 5.0 million tonnes per year, a full containment LNG storage, a LPG and condensate storage and a loading jetty. Angola LNG Limited awarded the contract for preparation of the plant site to the joint venture of Boskalis International B.V. and Jan de Nul Dredging Ltd., in which Boskalis had the lead. The preparation of the plant site consisted of widening and deepening the existing shipping channel in the ‘Baia de Diogo Cão’; dredging a turning basin for the LNG facility and improving the existing Kwanda Basin. The volume dredged was 28 million m3. The land reclamation works for the LNG facility consisted of raising 125 hectares of existing land on the north side of Kwanda Island and creating 65 hectares new land in the Congo river estuaria. The reclamation works required a total of 7 million m3 suitable material. Besides dredging and land reclamation, the works involved the construction of 1.5 km shore and slope protection, the installation of 4.5 km drainage around the fill areas, the installation and monitoring of geo instrumentation, the installation of a concrete oil/water separator and floodvalve as well as the placing of navigation aids in the channel and basins. The design and construct works were awarded by the end of January 2007, and all operations had to be completed by December 2008. The works entailed a highly challenging timeline and required a high degree of flexibility as the scope of work changed over time. This demanded maximum adaptability and fast decisionmaking, particularly in the design phase. Extensive environmental mitigation measures presented a further challenge, as did the unexploded bombs and other ordnance lying on the seabed in the area, a legacy from Angola’s 27-year civil war, which ended in 2002.

Related projects

Selected filters
29_Oct_04_D_isle__1__header.jpg

Construction drilling island and ice barriers, Kazakhstan

Agip Kazakhstan North Caspian Operating Company B.V. (Agip KCO), a consortium of eight leading oil companies, is active in the northern section of the Caspian Sea. The gas and oil reserves in this area were mapped out in 1998 and 1999. To allow for their exploitation, Boskalis International has created an artificial island measuring 225 x 225 meters, and underwater berms, for Agip KCO. Four years later, the time was ripe for the construction of the drilling island and ice barriers. Once they were in place, Agip KCO could start to extract and distribute the oil reserves.

LFH241124009_header.jpg

Cleanup petroleum harbor, Amsterdam

The Amsterdam Petroleum harbor on the North Sea Canal has been used for the storage and transshipment of oil products since its construction in 1887. Over many years routine operations and unchecked discharges resulted in severe contamination of the harbor.

Luchtfoto_milieubrochure_header.jpg

Cleanup, Ketelmeer

Ketelmeer, a lake in the Netherlands with a length of some 10 kilometers and a width varying from two to three kilometers, separates the North Eastern and Southern Polders constructed during the late 1960s and early 1970s. It is a major example of the problem of 'historic pollution'. Lake Ketelmeer receives the waters of the Rijn and IJssel and over a period of three or more decades, tens of millions of cubic meters of highly contaminated sediments entered Ketelmeer from hundreds of upstream locations. The bottom was covered by polluted sediments to an average depth of 50 cm. A significant proportion of this material had to be removed, or capped by the cleaner sediments of recent years, if a normal aquatic environment was to be restored.

Warnow_Tunnel__3__header.jpg

Tunnel construction Warnow, Rostock

The Warnow Tunnel is located in Rostock, Germany, at the old mouth of the river Warnow in the Baltic Sea. In the DDR period this area grew out to be the main harbor of East-Germany. After the 'turn' (die Wende) in 1989 the port more or less died. Goods came cheaper and quicker from Rotterdam, Bremen and Hamburg by rail.

Installation gas pipeline, Gelugor Mainline

The Gelugor transportation system is a 24'' gas pipeline from the Tenaga Nasional Berhad (TNB) Prai Power Station, Mainland Peninsular Malaysia across the Strait of Pinang to the TNB Gelugor Meter Station on Pinang island. The pipeline has a length of 6.4 km and was put into use in the beginning of 2000. Boskalis Offshore has constructed the protection of the pipeline with rock material. The function of the protection differs along the chainage of the pipeline. A shipping channel is situated between the island and the peninsular. The pipeline in the shipping channel has been covered for to protect against ship anchors (drop and drag).

Rosario_001_header.jpg

Fixed Link between Rosario and Victoria

The Joint Venture Boskalis International - Ballast Nedam JV was a subcontractor to the Consorcio Impregilo, Hochtief, Roggio and Techint which was awarded the construction of the fixed link between Rosario, in the province of Santa Fe and Victoria, in the province of Entre Rios. The Client in this project was the Argentine Government, and the leader of the Consorcio was Impregilo. The Consorciol executed all the civil constructions such as bridges while the JV Boskalis International – Ballast Nedam (BKI/BND) constructed, using sand only, the road embankments, connecting the several bridges.