The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

Project challenges

The main challenges, which were dealt with effectively during project preparation and execution, were:

  • The actual data for the FPSO was known at a very late stage of the project, considerably reducing the time available for the engineering phase;
  • The hull of the FPSO was stiffer than the hull of the DWV. This difference in the deflection characteristics of the two vessels resulted in high peak loads on the forward and aft ends of the cribbing wood and the FPSO hull when a sagging wave was introduced in the design phase. It was a huge engineering challenge to determine the best cribbing layout within a very short time. In the end, the cribbing beams at the bow and stern were reduced in height (by up to -40 mm) to manage the high peak loads exerted on the FPSO structure;
  • The water at the loading location was not deep enough to load the FPSO safely. A few days prior to loading, half a meter silt was dredged from the seabed to provide an underkeel clearance of 0.5 m during the submerging operation;
  • Access to the discharge location was a challenge in itself because of the shallow patches and wrecks in the approach channel. Good seamanship of the vessel’s crew, in combination with additional detailed navigational charts of the area and the early boarding of the pilot, ensured that the DWV arrived safely at the discharge location.

Conclusion

The Armada Intrepid FPSO was transported successfully from Rotterdam (Netherlands) to Batam (Indonesia). Dockwise provided the required service in time to the Client, dealing with all the given engineering and operational challenges. Evaluating the project preparation and execution, it can be concluded that a combination of operational best practices and engineering analysis was decisive for the safe, controlled and successful execution of the project.

Related projects

Selected filters
Fleet_OE_Moho.jpg

Transport and installation Moho Nord FPU

For the Total Moho Nord FPU project, Dockwise has transported the newbuild FPU Likouf from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Port-Gentil, Gabon. It was a world-record cargo load onboard a semi-submersible vessel to date. 

Thien_Ung_I.jpg

Installation topside
and living quarters,
Thien Ung BK-TNG

For the Vietsovpetro Thien Ung project, Boskalis has installed the Thien Ung BK-TNG 4,200 metric tonne (mt) topside and 850 mt living quarter by offshore heavy lifting with the sheerleg Asian Hercules III. It was the world’s heaviest lift installation of a topside by a sheerleg in an offshore environment to date. 

1407-0505-30_header.jpg

Development gas export pipeline, Ichthys

The Ichthys development revolves around the construction of a new 42-inch deep sea natural gas pipeline from the Ichthys field in the Browse Basin 880 kilometers to Darwin onshore. The pipeline will run through the Darwin harbor, requiring dredging services in the near shore area, rock installation and the construction of a landfall. Owner INPEX Operations Australia Pty Ltd is developing LNG process facilities on Blaydin Point near Darwin, Northern Territory of Australia.

140718_-_48.jpg

Wintershall RAVN and A6-A

Wintershall Noordzee B.V. installed a new remote platform RAVN as a crude production tie-back to A6-A. RAVN is a remote and unmanned crude well unit. Utilising a dry-tree design, all control, power and metered injection for the well will be via the 18.2-km control umbilical between the new satellite platform RAVN in the Danish sector and the operational platform A6-A in the German sector.

AT2C5860_header.jpg

Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

ZP_-_pic4_header.jpg

Mooring replacement phase 2, Zafiro Producer

Mobil Equatorial Guinea Incorporated, an affiliate of ExxonMobil, entered into a contract with Boskalis for the Zafiro Producer Mooring Replacement Project Phase 2. The Zafiro Producer is installed in 180 m (590 ft)water depth approximately 74 km (40 nauticalmiles) west of Malabo, Equatorial Guinea.