To main content

Fixed Link between Rosario and Victoria

The Joint Venture Boskalis International - Ballast Nedam JV was a subcontractor to the Consorcio Impregilo, Hochtief, Roggio and Techint which was awarded the construction of the fixed link between Rosario, in the province of Santa Fe and Victoria, in the province of Entre Rios. The Client in this project was the Argentine Government, and the leader of the Consorcio was Impregilo. The Consorciol executed all the civil constructions such as bridges while the JV Boskalis International – Ballast Nedam (BKI/BND) constructed, using sand only, the road embankments, connecting the several bridges.

The total length of the new road connection between Rosario and Victoria was 59 km of which 12 km were bridges and 47 km were embankments constructed from sand fills. There were one large bridge with a length of 3 km of the Rio Parana and 15 smaller bridges in the remaining 46 km. The execution of the Works for BKI/BND took 2 years. The works for BKI/BND consisted of:

  • The dredging of the top layers of clay to reach the sand layers underneath. This sand was needed for the construction of the embankments between the bridges. The volume of clay removed was approx. 11.000.000 m3.
  • The dredging of sand and creation of the road embankments with this sand. The volume involved was approx. 24.000.000 m3.
  • Temporary protection of the sand slopes of the road embankments with clay.
  • The dredging of a lateral channel with a length of 15 km for logistics purposes as well as the accesses to the several bridges under construction. The volume involved was 3.800.000 m3.

Related projects

Selected filters
IMG_0619_header.jpg

Port expansion, Gijón

The Spanish port of Gijón on the Bay of Biscay processes more than 12 million tonnes of bulk goods annually. With the expansion of global trade and increasing ship sizes, the terminal was lacking capacity to handle the traffic. The maximum draft for the ships of 18 meters is another obstacle to the development of the port. So the Port Authority of Gijón developed a plan for additional modern facilities in an area measuring 145 hectares to the north of the existing port. This includes a bulk terminal with a transfer capacity of more than 25 million tons and a storage area measuring 60 hectares for a maximum of 2 million tons of coal and iron ore a year.

5_Phase-2_header.jpg

Port development, Sevilla

Seville is located 80 km land inwards and it is Spain’s only commercial river port. Access is along the Rio Guadalquivir. The current dimensions and depth of the port impose limitations on the breadth and draughts of the vessels that use it, putting the future of the port at risk. So the Port Authority developed a New Maritime Approach that provides for the deepening and widening of the approaches to the port.

fremantle_1_header.jpg

Port expansion, Fremantle

Fremantle Ports is the Western Australian Government trading enterprise responsible for strategic management of the Port of Fremantle. The Port of Fremantle provides modern deep-water facilities for handling container trade, break-bulk vessels, livestock exports and motor vehicle imports as well as accommodating cruise ships.

IMGP4086.jpg

Extension cruise
terminal, the Bahamas

In April 2009 Royal Boskalis Westminster N.V. was awarded the contract for the extension of the cruise terminal in Nassau from the Ministry of Works and Transport of the Government of the Bahamas. The contract was worth approximately USD 44 million and the project was completed in the first six months of 2010.

_HP_0356_header.jpg

Dredging and reclamation, Port of Peterhead

The project consisted of capital dredging, reclamation, quay construction and breakwater extension works for Peterhead Smith Embankment Development, in order to develop the area in the north of the harbour at Smith Embankment to provide sheltered berths for vessels ranging from 20 to 160 m in length.

24012008_PLUTO_CSD_Phoenix__Samson_101_header.jpg

Dredging and construction, Pluto LNG project

The Pluto LNG project is located about 190 km northwest of the coastal town Karratha, in the Northern Carnarvon Basin, Western Australia. The project is a joint venture between Woodside Burrup Pty. Ltd., the operator, with a 90% interest, and Tokyo Gas (5%) and Kansai Electric (5%). The A$12 bn project will process gas from the Pluto and neighboring Xena gasfields.