To main content

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

During a survey campaign in 2006 initiated by the owners of the East Java Gas Pipeline, PT. Pertamina Gas and PT. Trans Javagas Pipeline, a large number of critical spans were identified, many of which above the threshold for vortex induced vibrations. Boskalis Offshore, through its Indonesian entity PT. Boskalis International Indonesia, was contracted to rectify 799 critical spans by means of installing a total of 804 rock berms. These berms reduce span lengths and prevent that the critical span length will be exceeded within the remaining lifetime of the pipeline.

Support Berm Installation 

For the support berm installation works Boskalis deployed its dynamically positioned fallpipe vessel (DPFV) Seahorse. This vessel, with a carrying capacity of 18,000 tons of rock, is able to position its fallpipe directly above the live pipeline, meanwhile ensuring sufficient vertical clearance to compensate for current and swell. The DP Class II capabilities of the vessel allow for accurate dumping with a minimum of losses resulting in a short project execution time. One load of 1-5' rock was brought from Norway and additional loads were loaded in Indonesia. Rock was supplied by a quarry operating in the inlands of East Java, delivering rock via the road to a temporary stockpile at the port of Paiton. During loading the 1-5' rock was transported by truck from the temporary stockpile to the feeder and via a conveyor belt into the holds of the DPFV Seahorse. The entire temporary supply chain for rock supply, from quarry to Seahorse, was purposely set up for the execution of this project. Prior to commencement of the rock dumping operations, a pre-survey was carried out by Seahorse's ROV, equipped with multibeam echosounders. This survey was used to identify the start and end points of the free spans. Subsequently, the design per span location was prepared and the berms were installed. A post-survey was carried out to ensure that the berms were installed as specified. When the results of the post-survey were satisfactory, the vessel moved to the next position.

Related projects

Selected filters

Installation gas pipeline, Balgzand-Bacton

BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m3 of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.