The Jotun A FPSO, a 92,000 DWT FPSO capable of producing 70,000 bpd, began producing in 1999 on the Jotun field (Norway). As part of Vår Energi’s investment in increased oil recovery from the Balder field in the North Sea an upgrade of the Jotun FPSO is required. The Balder Future project will extend the life of the field (PL 001) by 2045, giving Norway’s oldest license a lifetime of 80 years.

Boskalis performed the engineering and prepared the method statements for the lift off activities from the Jotun A FPSO its turret, gantries and turntable.Due to the outreach, height and capability one of the few sheerlegs capable to execute same is the Taklift 4. The lifting was executed in Stavanger (Norway) by the Taklift 4 with 30 meters fly-jib assisted by AHT Sapphire, both Boskalis own equipment, and under guidance of a Boskalis Heavy Lift Supervisor.

The upgrade was contracted under the coordination of Rosenberg Worley in Stavanger. The upgrade includes an overhaul of the turret, pipes, process equipment, hulls, marine systems, living quarters, control and security systems. The FPSO is scheduled to be re-installed between the Balder FPSO and the Ringhorne platform during summer 2022.

Related projects

Selected filters
005dd16062014Boskalis-_c_Kloet_header.jpg

Transport and installation depletion compression platform,
Malampaya phase 3

The Malampaya Deep Water Gas-to-Power Project is a joint venture involving the Philippine National Oil Company, Chevron and Shell Philippines Exploration. The project is part of the optimization of the Malampaya gas field which will lead to an eight-year lifetime extension.

SMIT_Subsea_Constructor-MaerskOil_Dan_56768_header.jpg

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

Fairmount_Sherpa_assisted_by_local_harbor_tugs_towing_in_the_FPSO_at_Haugesund_header.jpg

Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

140718_-_48.jpg

Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

DONG_Rockpiper_West_of_Duddon_Sands_header.jpg

Wind farm foundation installation, West of Duddon Sands

With 108 wind turbines producing almost 400 megawatts, West of Duddon Sands is one of the larger European wind farms. It is being built by a joint venture of Dong Energy and Scottish Power Renewables. Boskalis Offshore and Volker Stevin Offshore - in an Offshore WindForce joint venture - were responsible for the transport and installation of the 108 foundations for the wind farm.

Java-Bali_header.jpg

Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.