Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

The contract for the North Manama Causeway project, situated in the Diplomatic area north of the capital Manama in the Kingdom of Bahrain, was secured by Boskalis Westminster Middle East through an open public tender process. A variation to the original contract scope required the design optimization and construction of a land mass which included a reclamation, revetments, five breakwaters, a dredged navigation channel and storm water outfalls.  The integration of Hydronamic engineers into the Project Team brought together the technical insight and knowledge of the design team and the practical knowledge and experience of the Contractor. The project team developed innovative ideas to optimize rock protection design, leading to a successful and efficient construction with significant cost savings to the project. 

Optimization during design and preparation phase

The contract variation was awarded on a lump sum basis and called for the design and construction of the land reclamation and associated rock and auxiliary works. Engineering department Hydronamic were engaged to execute the conceptual, preliminary, and detailed final design of the breakwaters and rock protection. The Environmental Impact Assessment (EIA) was prepared by Hyder Consulting. Hydronamic developed an Environmental Management Plan to meet the requirements set out in the EIA, and the Project Team implemented the plan during construction.

Related projects

Selected filters
IMG_8772_header.jpg

Coastal protection, St. Petersburg

St. Petersburg is a UNESCO World Heritage City, but its location along the River Neva means that it has been threatened by over 300 floods since its founding by Peter the Great in 1703. The completion of the new 25 km long storm-surge barrier across the Gulf of Finland ensures that the city will no longer be vulnerable to high tides and devastating floods. As a result of the new Flood Protection Barrier, however, the old winding access channel had to be replaced with a new, straighter, more easily navigable channel.

Delflandse_coast___3__header.jpg

Coastal protection, Delfland coast

In August 2008 Van Oord and Royal Boskalis Westminster N.V. have been awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce a weak link in the Delflandse coast . The contract is worth EUR 120 million of which Van Oord and Boskalis have an equal share.

IMG_1888_header.jpg

Cleanup, Zellingwijk area

The Zellingwijk quarter of the village of Gouderak was built in the middle of the last century. In the early 1980s it became clear that the soil underneath this residential area was heavily contaminated as a result of the dumping of waste - mainly mineral oils and pesticides. The homes built on the site were subsequently demolished in the mid-1980s. Pending definitive remediation work, a layer of concrete / asphalt was applied to seal the site.

DSCF0279_header.jpg

Overview activities, Bahrain

The Kingdom of Bahrain is an island located in the Gulf, east of Saudi Arabia and north of Qatar and connected with its neighbour Saudi Arabia since the year 1980 with a 25 km long causeway. The archipelago consists of some 30 islands with a total of 160 km of shoreline and has a population of 800,000. Whereas the surface of Bahrain in the year 1960 was around 650 km2, the last decennia have seen a steady increase in the surface till a respectable figure of 740 km2 in 2007. This increase has been achieved by a various number of small and mayor reclamation projects.

37ac96e429c252fd55f1136ce6374c9e_image_header.jpg

Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

IMG_0619_header.jpg

Port expansion, Gijón

The Spanish port of Gijón on the Bay of Biscay processes more than 12 million tonnes of bulk goods annually. With the expansion of global trade and increasing ship sizes, the terminal was lacking capacity to handle the traffic. The maximum draft for the ships of 18 meters is another obstacle to the development of the port. So the Port Authority of Gijón developed a plan for additional modern facilities in an area measuring 145 hectares to the north of the existing port. This includes a bulk terminal with a transfer capacity of more than 25 million tons and a storage area measuring 60 hectares for a maximum of 2 million tons of coal and iron ore a year.