To main content

Offshore wind farm
monopile installation,
Veja Mate

Boskalis is close to completing one of its latest and most significant offshore wind projects - Veja Mate, in the German North Sea. The project involves handling and installing the biggest monopiles in the industry – weighing between 1,230-1,302-tonne a piece – using the biggest pile gripper frame and pile driving hammers in the industry with a brand new vessel, which also happens to be the biggest in the sector. Once complete, the offshore wind farm will produce over 1,6 TWh of green, renewable electricity annually.

The wind farm is located in the German North Sea, ~95 km NW from Borkum island in the German Exclusive Economic Zone, an area with strong, steady winds. The water depth is 39 - 41 meters. After first getting involved during the first quarter of 2015, Boskalis was awarded the EPCI contract for design, procurement, fabrication, supply, transportation, installation and testing for 67 wind turbine foundations in the summer of 2015.  The project team hit the ground running and encountered challenges: design was already initiated by the client with a design sub-contractor and fabrication was already up and running. Boskalis was also dealing with installation equipment and methods for the 85-meter-tall monopiles the size of which no one had handled before. In addition, everything for transport and installation had to be designed, ordered and built for this project in 10 months.

Pile gripper frame

An extremely focused project team project team put everything on a critical path to ensure that the project stayed on track. Boskalis’ Hydrodynamics engineering department determined the need for a two level pile gripper frame to minimize the impact of the piles swinging when lowering; Boskalis utilized lean planning guidance for the pile gripper fabrication and the installation works were contracted as a package to Seajacks. Construction of the monopiles in Rostock, Germany started soon after contract close. The 350-tonne a piece transition pieces were fabricated in Aalborg, Denmark. From both sites the components were transported to a marshalling yard at Eemshaven, the Netherlands ready for installation.

Monopile installation

A new generation jack-up installation vessel, the SeaJacks Scylla, with a crane that can handle 1,500 tonnes installed the monopiles and the SeaJacks Zaratan transported and installed the transition pieces. Offshore installation involved transporting three monopiles at a time on the Scylla and six transition pieces at a time on Zaratan. Having multiples of three helped to keep the project in sequence. Each pile-driving operation took about 24 hours, including driving through the previously laid scour protection. Scour protection was done using Boskalis’ rock placement vessel the Rockpiper, once unexploded ordnance detection and removal was carried out across the site.

Mitigating underwater noise

Minimizing under water noise on the project was the next challenge. “Mitigating underwater noise comes with strict requirements in Germany and these are the largest piles, at the biggest water depth using the biggest hammer. To be allowed to drive the piles, Boskalis had to prove that the systems kept the noise to an agreed limit. Successful results came after switching contractors and using a hydrosound damper on the gripper frame as well as a double bubble curtain.

Project completion

The project team completed the installation of all the foundations in the fall of 2016. Rasmus Miller, Foundation Package Manager, said “Project work has its ups and downs, but it is never boring. We had our fair share of challenges to overcome and without everyone staying ahead of the game, it was close to impossible to achieve project success. I am therefore extremely proud to say that everyone on our Veja Mate and Boskalis teams, stepped up to the plate and tackled our challenges head-on.” The next steps in the construction of the wind farm will be to complete the energization of the Offshore Substation, the installation of the inter array cables and subsequently the wind turbines. The project is expected to be fully operational by the end of 2017.

Related projects

Selected filters
Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.