Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

The pipe laying has been executed by Hyundai Heavy Industries Co. Ltd (HHI). Boskalis was awarded a subcontract to execute the pre-trenching, backfilling and landfall works from the Landfall Point to 19.5 kilometers offshore (from Port Limits). Project preparations commenced in August 2004 and all operations were completed in May 2005 well before the start of the monsoon season. Upon completion of the operations within the Port Limits Boskalis was requested to use their expertise for the post-trenching of both pipelines until 130 kilometers offshore.

Pre-Trenching Operations

A trench was dredged to a width of 8 meters in the near-shore section (1.6 kilometers) and to a width of 10 meters further offshore. Soil conditions in the area varied between very soft silty clay and weathered basalt. In the case of hard material, a cover of 1 meter on top of the pipeline was required, in the case of soft material a cover of 3 meters. Three dredging units, each with its own specific features, were mobilized for the operations. The backhoe dredger Colbart dredged the near-shore part of the trench, where the water depth limited the activities of the hopper dredgers, and the sections where hard material was encountered. To pre-handle sections with hard material, the Colbart was fitted out with a S35 hydrohammer. The trailing suction hopper dredgers Flevo and Seaway were mobilized to dredge the shallow parts of the trench and the offshore section respectively. The dredged material was deposited in a temporary storage area at 1 kilometer distance from the trench to be re-used for backfilling.

Related projects

Selected filters
005dd16062014Boskalis-_c_Kloet_header.jpg

Transport and installation depletion compression platform,
Malampaya phase 3

The Malampaya Deep Water Gas-to-Power Project is a joint venture involving the Philippine National Oil Company, Chevron and Shell Philippines Exploration. The project is part of the optimization of the Malampaya gas field which will lead to an eight-year lifetime extension.

SMIT_Subsea_Constructor-MaerskOil_Dan_56768_header.jpg

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

Fairmount_Sherpa_assisted_by_local_harbor_tugs_towing_in_the_FPSO_at_Haugesund_header.jpg

Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

140718_-_48.jpg

Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

DONG_Rockpiper_West_of_Duddon_Sands_header.jpg

Wind farm foundation installation, West of Duddon Sands

With 108 wind turbines producing almost 400 megawatts, West of Duddon Sands is one of the larger European wind farms. It is being built by a joint venture of Dong Energy and Scottish Power Renewables. Boskalis Offshore and Volker Stevin Offshore - in an Offshore WindForce joint venture - were responsible for the transport and installation of the 108 foundations for the wind farm.

Java-Bali_header.jpg

Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.