To main content

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

The pipe laying has been executed by Hyundai Heavy Industries Co. Ltd (HHI). Boskalis was awarded a subcontract to execute the pre-trenching, backfilling and landfall works from the Landfall Point to 19.5 kilometers offshore (from Port Limits). Project preparations commenced in August 2004 and all operations were completed in May 2005 well before the start of the monsoon season. Upon completion of the operations within the Port Limits Boskalis was requested to use their expertise for the post-trenching of both pipelines until 130 kilometers offshore.

Pre-Trenching Operations

A trench was dredged to a width of 8 meters in the near-shore section (1.6 kilometers) and to a width of 10 meters further offshore. Soil conditions in the area varied between very soft silty clay and weathered basalt. In the case of hard material, a cover of 1 meter on top of the pipeline was required, in the case of soft material a cover of 3 meters. Three dredging units, each with its own specific features, were mobilized for the operations. The backhoe dredger Colbart dredged the near-shore part of the trench, where the water depth limited the activities of the hopper dredgers, and the sections where hard material was encountered. To pre-handle sections with hard material, the Colbart was fitted out with a S35 hydrohammer. The trailing suction hopper dredgers Flevo and Seaway were mobilized to dredge the shallow parts of the trench and the offshore section respectively. The dredged material was deposited in a temporary storage area at 1 kilometer distance from the trench to be re-used for backfilling.

Related projects

Selected filters

Installation gas pipeline, Balgzand-Bacton

BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m3 of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.