Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m<sup>2</sup> container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.

Work for WDC included dredging approximately 6.1 million m3 consisting of:

  • Dredging of silts and soft clays within reclamation terminal footprint (approx. 50,000 m3);
  • Reclamation works to fill the area between the present quay and future quay wall including former Felixstowe Dock Basin (approx. 3,000,000 m3 including 500,000 m3 re-use material from channel widening);
  • Dredging/widening of western section of the approach channel (2,000,000 m3 including 500,000 mre-use material);
  • Dredging of deep water berth pocket in front of the new quay wall (3,000,000 m3);
  • Dredging of future tug berth pockets (50,000 m3).

The design of the project, including various stages of the dredging and reclamation works as well as the sequencing of the quay wall installation, ensured stability and a secure work area throughout the project and resulted in a successful product for the end users delivered on time.

Related projects

Selected filters
Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.

hires-6917.jpg

Construction motorway, A4 Delft-Schiedam

Boskalis Nederland was involved in the construction of the A4 motorway from Delft to Schiedam. The client is Rijkswaterstaat. After 40 years, the construction of this final section will bring to an end the public debate about whether this new road was needed.

Boskalis_Suezkanaal_cutter_suction_dredgers_4153_header.jpg

Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

DSC_0008_header.jpg

Onshore co-mining project, Lelydorp

Suralco L.L.C., an indirect joint subsidiary of Alcoa Inc. and Alumina Ltd., has awarded Boskalis a contract for the mining of bauxite in Lelydorp, Suriname. Boskalis is responsible for the entire mining process, from engineering and overburden removal to bauxite mining and ore delivery.

Picture_6_header.jpg

Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

P1030713_header.jpg

Dredging and reclamation, Songdo International City

Boskalis has been awarded a contract by Daewoo E&C for the dredging and reclamation of new land for Songdo International City on the waterfront of Incheon, South Korea. The total value of the contract amounts to approximately EUR 80 million.