Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.

The cables have the capability to transfer power at 130 MVA per circuit. This project will provide enough additional power to solve Bali's shortage and facilitate the further development of a popular tourist destination, which attracts around 2.3 million tourists each year. Boskalis’ scope ran roughly from the high water mark at Ketapang, Java, to the high water mark at Gilimanuk, Bali and involved the installation of the two submarine cables, including four cable landings. After cable installation, both cables had to be covered with a rock berm over nearly the entire length of the routes. The newly built Cable Laying Vessel (CLV) Ndurance was deployed for the cable installation.

Engineering

One of the most complicating factors was the extremely strong current which occurs in the Bali Strait. Boskalis’ in-house engineering company Hydronamic was involved to analyze the most efficient installation method and period. Based on a current measurement campaign, which lasted over one year, the most favorable installation window was determined. Since Boskalis was also responsible for the cable routes design, an extensive hydrographic survey was undertaken to map the seafloor. This survey and the design parameters specified by the Client were used to design the optimum cable routes, taking the properties of the cables into account. Mitigation of free spans and vortex induced vibrations (VIV) formed part of the engineering work, coordinated by Boskalis' affiliate VBMS. To assess the station keeping capabilities of the Ndurance at this specific location with very strong currents, a series of simulations was performed at the Marin ship simulator. Based on these simulations, it was decided to have an Azimuth Stern Drive (ASD) tug boat stand-by in the direct vicinity of the CLV during cable lay operations to avoid any risk for crew, vessel and cable. Extensive sea trials were undertaken in Singapore and on site to practice and determine the behavior of the Ndurance and the combination of CLV and ASD tug.

Related projects

Selected filters
Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.