<div>The Wikinger offshore wind farm has been developed by Iberdrola in the Baltic Sea area, within the German Exclusive Economic Zone (EEZ). The offshore site is about 34 km northeast of the island of Rügen, and covers an area of roughly 50 km², within which 70 wind turbine generators (WTG) of 5 MW and one offshore substation (OSS) are being installed. The water depths for installation range between 36 and 42 meters. When completed the windfarm will deliver 350 MW electrical power to the German national grid. The transport and installation of the 70 WTG foundations and the piles for the OSS has been carried out by Boskalis.</div>

Foundations

Each of the WTG foundations consists of a four legged jacket including a transition piece and four piles. Lengths and weights vary due to different water depths and soil conditions. The piles are driven into the soil prior to jacket installation (pre-piled foundation concept). Furthermore the piles are dredged and cleaned internally prior to jacket installation. After installation of the jacket the connection between the jacket and the piles has been realized by grouting.

Transport

A significant part of the Boskalis scope comprises the safe transportation of the piles and jackets from their fabrication sites in Seville, Aviles and Fene-Ferrol, Spain, and from Lindø and Aalborg, Denmark to the Iberdrola feeder port in Sassnitz, Germany. A variety of assets has been deployed for the transportation. Piles are transported using tugs and barges for the transports from Aalborg and geared vessels from Seville and Aviles. Jackets from Lindø are also transported by tugs and barges. The transport from Fene-Ferrol via the Bay of Biscay and the North Sea to the Baltic Sea has been done by Dockwise S-class vessels (Swan and Tern) on 7 consecutive voyages transporting 4 jackets each voyage.

Installation

Installation of the jacket foundations comprises four consecutive steps. The piles are driven into the seabed using a specially designed self levelling pre-piling template able to position the piles to the exact tolerances. The piles are driven by a 1200 kJ hydro-hammer. The template and hammer spread are deployed from the Giant 7 converted for the Wikinger Project into an offshore crane barge by installing a 1000 t Liebherr crane. Once installed the piles are dredged and cleaned using specialist tools deployed from two DP vessels. Jackets are installed with one of the Boskalis sheerlegs Taklift 4 with a capacity of 1400 t. After installation the annulus between the jacket legs and the piles has been grouted using high strength grout pumped from a grout factory deployed from another DP vessel. After grouting the jacket foundation has been inspected and handed over to the client.

Tailor made vessel and specialist tools

A wide range of self-owned vessels have been deployed on the Wikinger project ranging from support vessels, multicats, tugs, barges, a rock dumping vessel, installation vessels and one of our sheerlegs. In addition various support vessels, tugs and barges were hired on the project. In total some 25 vessels were deployed.

Noise mitigation

Noise mitigation measures are in place during pile driving to meet the strict requirements set by the German Authorities for pile driving in the Baltic Sea. Three noise mitigation measures have been applied:

  • Double big bubble curtain on the sea bottom around the template and the installation vessel (Giant 7)
  • Small bubble curtain around each of the four cages of the pre-piling template
  • Hydro sound damper deployed around the pile (contingency in case the criteria are not met)

All installation activities have been executed well within the noise limits ISO requirements.

Conclusion

Boskalis has proven its capability to execute complex projects to the highest safety and environmental standards overcoming difficult technological challenges using tailor made vessels and equipment.

Related projects

Selected filters
005dd16062014Boskalis-_c_Kloet_header.jpg

Transport and installation depletion compression platform,
Malampaya phase 3

The Malampaya Deep Water Gas-to-Power Project is a joint venture involving the Philippine National Oil Company, Chevron and Shell Philippines Exploration. The project is part of the optimization of the Malampaya gas field which will lead to an eight-year lifetime extension.

SMIT_Subsea_Constructor-MaerskOil_Dan_56768_header.jpg

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

Fairmount_Sherpa_assisted_by_local_harbor_tugs_towing_in_the_FPSO_at_Haugesund_header.jpg

Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

140718_-_48.jpg

Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

DONG_Rockpiper_West_of_Duddon_Sands_header.jpg

Wind farm foundation installation, West of Duddon Sands

With 108 wind turbines producing almost 400 megawatts, West of Duddon Sands is one of the larger European wind farms. It is being built by a joint venture of Dong Energy and Scottish Power Renewables. Boskalis Offshore and Volker Stevin Offshore - in an Offshore WindForce joint venture - were responsible for the transport and installation of the 108 foundations for the wind farm.

Java-Bali_header.jpg

Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.