Wintershall RAVN and A6-A

Wintershall Noordzee B.V. installed a new remote platform RAVN as a crude production tie-back to A6-A. RAVN is a remote and unmanned crude well unit. Utilising a dry-tree design, all control, power and metered injection for the well will be via the 18.2-km control umbilical between the new satellite platform RAVN in the Danish sector and the operational platform A6-A in the German sector.

The umbilical forms the entire link between the remote platform, supplying and controlling all functions and ensuring continual feedback and monitoring of RAVN.

The umbilical supplies all the necessary input data, control and feedback to eliminate the usual day-to-day requirements of direct human contact. The umbilical was installed from RAVN first end to second end pull-in at A6-A end. Platforms are located in the Danish territorial waters in the North Sea (RAVN) and German territorial waters in the North Sea (A6-A). The umbilical was connected/pulled into RAVN via a J-tube and internal conductor to the RAVN topside -TUTA. RAVN - first end with pull-in to topside deck via a J-tube - was laid in corridor separate from the 8-inch pipeline between RAVN and A6-A and second end pull-in using the quadrant method at the A6-A platform.

SCOPE OF WORK

  • Prepare project planning for Boskalis’ scope of work.
  • Survey work, including post-burial survey.
  • Perform route engineering and installation engineering to optimize the performance of the installation scope, including Orcaflex analysis for laying, pull-ins, loads and dynamics, as well as a detailed burial assessment study (BAS).
  • Prepare platform on RAVN and A6-A.
  • Define umbilical length together with the client.
  • Umbilical load-out at Hartlepool (UK) onto the installation vessel Ndurance.
  • Installation and hang-off of umbilical termination heads – topsides.
  • Crossing 36- & 40-inch live gas pipelines.
  • Pull-in at RAVN & A6-A platforms – direct from vessel as part of SIM-OPS.
  • Umbilical lay and bury scope – minimize on seabed exposure.
  • Mobilize and demobilize all installation spreads for Boskalis’ scope.
  • Provide engineering support during the offshore umbilical installation, including simultaneous burial.
  • Provide QHSE management for Boskalis’ scope.
  • Process and deliver as-built data.
  • Mobilize and demobilize all installation spreads for Boskalis’ scope.

Related projects

Selected filters

Gas pipeline project, Trans Thailand Malaysia

The Trans Thailand Malaysia Gas Pipeline Project comprised the installation of a 34 inch concrete coated gas pipeline, running from the joint Thai-Malaysia development area approximately 270 kilometers offshore towards the southern Thai coast near Chana. As part of this project a contract was awarded to the Boskalis Offshore B.V. - Tideway B.V. consortium for the provision of the dredging and backfilling works, whereas Boskalis Offshore provided the main equipment and project support.

Seahorse_04_header.jpg

Glory hole excavation, White Rose

The White Rose offshore oil field is the third major oil field in the Jeanne d’Arc Basin on the Grand Banks, some 350 kilometers east of St. John’s, Newfoundland, Canada and within 50 kilometers from the Terra Nova and Hibernia fields. The South White Rose oil pool covers approximately 40 square kilometers and contains an estimated 200-250 million barrels of recoverable oil.

Development gas export pipeline,
Hibiscus to Point Fortin

The NCMA Development Project comprised the development of the North Coast Marine Area, which is located in the Caribbean Sea and Bay of Paria, Trinidad. The project included the installation of a 24" Gas Export Pipeline from the Hibiscus Platform to a landfall at Point Fortin. From the landfall the pipeline was routed by directional drilling and by surface laid pipeline, to a termination point in the Atlantic LNG Terminal at Point Fortin. As part of this project Boskalis was awarded the contract for the provision of landfall, directional drilling and onshore pipeline installation and testing of the 24" gas pipeline system.

Sandpiper_foto_offshore_2_header.jpg

Hanze F2a Development Project

Hanze, 200 kilometers offshore Den Helder in block F/2 of the North Sea, is the first operated development in the Dutch sector by Germany's Veba Oil. The oilfield reserved approximate 34 million bbl, plus 40 bcf of associated gas. 

Installation gas pipeline, Takoradi

Late November 1998 Boskalis was awarded a subcontract for the installation of two marine pipelines to supply and discharge cooling seawater for the Takoradi thermal power plant that was under construction for the Volta River Authority, near the village of Aboadze approximately 20 kilometers north-east of Takoradi, Republic of Ghana.

WD_Fairway_and_Sandpiper_near_platform_header.jpg

Re-insulation Gannet 'C' Bundles, North Sea

The Gannet 'C' satellite field, which is located in the North Sea at 112 miles East of Aberdeen in 95-meter water depth, comprises four drill centres, each having one or more producing wells. The drill centres are connected to the local platform Gannet 'A' by four flowline bundles with a total length of 10 kilometers. A glycol-based gel, filling the annulus of the Gannet 'C' carrier pipe, insulated the individual flow lines. Prompted by degradation of the gel and the resulting drop in oil and gas arrival temperatures at the platform, an EPIC project took off for a re-insulation system. The objective of the re-insulation system was that it should provide sufficient insulation to the bundles in order to safeguard production during the total field life of Gannet 'C', being a minimum lifetime of 15 years. Boskalis Offshore was supported by Hydronamic - the in-house engineering department.