Borssele ALPHA/BETA

Royal Boskalis Westminster is a leading global marine contractor and services provider. With safety as our core value, we offer a wide variety of specialist activities to the oil & gas and renewa-bles sectors. These activities include marine instal-lation and decommissioning, seabed intervention, marine transport and services, subsea services and marine survey. In addition, Boskalis is a global dredging contractor, provides towage and terminal services across the globe and delivers marine salvage solutions. By understanding what drives our clients we are able to provide the solutions that enable them to meet their specific business goals. For this reason we are constantly looking for new ways to broaden and optimize our offering and are committed to expanding our proposition, supported by our financial strength. With our committed professionals in engineering, project management and operations, 800 special-ized vessels and an unprecedented breadth of activities in 90 countries across six continents we help our clients in the offshore industry push boundaries and create new horizons.

LONG-TERM DRIVERS APPLICABLE TO THE PROJECT

Generating renewable energy. Increasing energy consumption.

PROJECT CONTEXT

In the Agreement for Sustainable Growth from the Dutch government, it has been agreed that in 2023, 16 percent of the Dutch energy-supply needs to come from sustainable sources. To achieve this goal, the Netherlands need to generate more wind-energy, both on land and sea.

INTRODUCTION

The grid connection of the Borssele offshore wind area in the North Sea consists of two 700 MW connections, called Alpha (for Borssele I and II) and Beta (for Borssele III and IV). Boskalis Subsea Cables, in consortium with NKT, was awarded the contract for the supply and installation of 4 export cables and 1 intercon-nector cable. In order to execute the project in a safe and efficient manner, Boskalis has taken full advantage of the expertise and capabilities within the group. To allow the cables to be installed, shallow parts of the route are dredged and sand-waves are pre-sweeped.

BSS-III

For the project, cable burial up to 10 meters depth was required. To achieve this, a trench of 2 meters was dredged. Then the Boskalis inhouse designed burial sledge BSS-3 lowered the cable another 8.5 meter. The BSS-III is capable to bury the cables up to 8.5 m in sand and 6.5 m in hard clay. A world record for cable burial. Using the tool, Boskalis managed to limit the amount of dredging in the NATURA2000 area Westerschelde and therefore minimizing the impact on the unique environment of this nature protection area.

Related projects

Selected filters
TSHD_Barent_Zanen_backfilling_at_Denia_header.jpg

Landfall construction
Balearic submarine pipeline

As part of its network expansion program, Enagas undertook the installation of a submarine pipeline providing natural gas from the Spanish mainland to the Balearic Islands of Ibiza and Mallorca, integrating them into the Spanish gas system. This 20" nominal diameter pipeline was constructed in two distinct sections, one of 123 km between the mainland and Ibiza and another of 146 km between Ibiza and Mallorca.

Baydaratskaya_Bay.jpg

Installation gas pipeline, Baydaratskaya Bay

The Baydaratskaya Bay Project is located in the Kara Sea in the North of Russia. The Kara Sea is bordered on its western side by Novaya Zemlya and on the east by the North Siberian Coast. Baydaratskaya Bay is located in the south of the Kara Sea between the Ural Coast and the Yamal Peninsula. Yamalgasinvest (Gazprom) is planning the construction of four pipelines and two cable crossings at Baydaratskaya Bay for the exploitation of the Bovanenkova and Harasawejskoje gas field on the Yamal Peninsula.

DPFV_Seahorse_moors_for_loading_header.jpg

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

Installation_of_cofferdam_to_enable_trench_excavation_through_surf_zone_header.jpg

Crude oil unloading facilities, Sri Racha

Thai Oil Public Company Limited is the largest petroleum oil refiner and supplier in Thailand. To enable Very Large Crude Carriers (VLCC) up to 320,000 DWT or a freight capacity of up to two million barrels to berth at Thai Oil's refinery in Sri Racha, Chonburi Province, a second Single Buoy Mooring (SBM) facility was installed approximately 14 km offshore, in water depths of around 30 m. From this buoy, a 52' diameter concrete coated steel pipeline had to be installed to the landfall location near the Thai Oil refinery.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.