Royal Boskalis Westminster is a leading global marine contractor and services provider. With safety as our core value, we offer a wide variety of specialist activities to the oil & gas and renewa-bles sectors. These activities include marine instal-lation and decommissioning, seabed intervention, marine transport and services, subsea services and marine survey. In addition, Boskalis is a global dredging contractor, provides towage and terminal services across the globe and delivers marine salvage solutions. By understanding what drives our clients we are able to provide the solutions that enable them to meet their specific business goals. For this reason we are constantly looking for new ways to broaden and optimize our offering and are committed to expanding our proposition, supported by our financial strength. With our committed professionals in engineering, project management and operations, 800 special-ized vessels and an unprecedented breadth of activities in 90 countries across six continents we help our clients in the offshore industry push boundaries and create new horizons.

LONG-TERM DRIVERS APPLICABLE TO THE PROJECT

Generating renewable energy. Increasing energy consumption.

PROJECT CONTEXT

In the Agreement for Sustainable Growth from the Dutch government, it has been agreed that in 2023, 16 percent of the Dutch energy-supply needs to come from sustainable sources. To achieve this goal, the Netherlands need to generate more wind-energy, both on land and sea.

INTRODUCTION

The grid connection of the Borssele offshore wind area in the North Sea consists of two 700 MW connections, called Alpha (for Borssele I and II) and Beta (for Borssele III and IV). Boskalis Subsea Cables, in consortium with NKT, was awarded the contract for the supply and installation of 4 export cables and 1 intercon-nector cable. In order to execute the project in a safe and efficient manner, Boskalis has taken full advantage of the expertise and capabilities within the group. To allow the cables to be installed, shallow parts of the route are dredged and sand-waves are pre-sweeped.

BSS-III

For the project, cable burial up to 10 meters depth was required. To achieve this, a trench of 2 meters was dredged. Then the Boskalis inhouse designed burial sledge BSS-3 lowered the cable another 8.5 meter. The BSS-III is capable to bury the cables up to 8.5 m in sand and 6.5 m in hard clay. A world record for cable burial. Using the tool, Boskalis managed to limit the amount of dredging in the NATURA2000 area Westerschelde and therefore minimizing the impact on the unique environment of this nature protection area.

Related projects

Selected filters
Seahorse_-_Nord_Stream_2032010_header.jpg

Trench dredging gas pipeline, Nord Stream

The Nord Stream gas pipeline project is a joint project of four major companies: Gazprom, BASF/Wintershall, E.ON Ruhrgas and Gasunie. The project is more than just a pipeline. It is a new channel for Russian natural gas exports and a major infrastructure project which is expected to set a new benchmark in EU-Russia cooperation. In view of current developments the new pipeline will be an important factor of energy security in Europe.

D1107-1233_header.jpg

Seabed preparatory works,
Dana Medway

Dana Petroleum Netherlands B.V. is the operator of the Pllb De Ruyter field and oil-producing platform located in the Dutch section of the North Sea.

DPFV_Sandpiper_accompagnied_by_SMIT_tugs_on_her_way__to_worksite_header.jpg

Rock installation, PDET

In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

Belwind_1_bewerkt_header.jpg

Construction wind farm, Belwind

SMIT sheerlegs Taklift 4 installed the final element for one of Belgium’s first offshore wind farms, Belwind, the wind farm’s high voltage transformer substation. SMIT also provided the transport of the element and other marine support services to assist the construction of the wind farm.

Walney_wind_farm_UK_support_installatie_monopiles_windmolens_header.jpg

Offshore wind farm, Walney

Windfarm construction projects regularly feature in the work programmes of SMIT’s sheerlegs fleet. For example, the Taklift 7 was involved in the Walney Offshore Windfarm development in the Irish Sea. Walney Offshore is a wind farm project developed by DONG in the Irish Sea, some 20 miles from the coast at Barrow.

Magellan_4_header.jpg

Pipeline crossing, Strait of Magellan

The project involved the construction of a new, strategically important, 24" natural gas pipeline across the Strait of Magellan, linking Cabo Espíritu Santo in Tierra del Fuego province with Cabo Vírgenes in Santa Cruz province. The new pipeline was built as an expansion of the existing San Martín pipeline in an effort by the government to increase gas supplies from Tierra del Fuego to the Argentinian mainland.