Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

The infield cables were loaded in one load-out at Drammen in Norway and then cut down to the correct size on site. The WTGs were connected in a grid of infield cables. 86 individual cables were installed between the turbines, including 6 redundancy cables, amounting to a total length of approximately 90 km for the infield cabling. Cable production commenced in December 2013. The cables were installed in the summer of 2014 using the Stemat Spirit. This vessel was converted to enable the handling of the long cable protection system lengths. Trenching of the cables was performed using a separate trenching spread. Termination, testing and commissioning of the 12 cable strings were carried out using in-house resources.

Related projects

Selected filters
DSC03484_header.jpg

Cleanup, Westergasfabriek

The Westergasfabriek was built by the British firm Imperial Continental Gas Association (ICGA) in 1883, and was at the time the biggest coal-fired gas factory in Amsterdam. The project site, covering four hectares, housed coal storage yards, gasometers, purification plants, a water tower and office buildings, all designed by the famous Dutch architect Isaac Gosschalk. The municipal energy company used the site for storage into the early 1990s.

Bahrain_header.jpg

Land reclamation, Shaikh Khalifa Bin Salman Causeway

The Shaikh Khalifa Bin Salman Causeway is located in the State of Bahrain in an expanse of water called the Khawr Al Qulayah. It connects the Hidd Drydock Highway to the Mina Sulman Port. This major infrastructure project is carried out in advance of the planned expansion of the Bahrain port activities. This New Port project is planned at the Hidd side and via the Shaikh Khalifa Bin Salman Causeway direct connected with the existing Mina Sulman port and Saudi Arabia. The total length of the Shaikh Khalifa Bin Salman Causeway is approximately 6,500 m, including a bridge of 400 m, which was constructed in 2000.

Oresund.jpg

Tunnel construction Øresund, Denmark - Sweden

The Øresund Tunnel forms part of the Øresund Link that connects the cities of Copenhagen in Denmark and Malmö in Sweden across the Øresund.

Chek_Lap_Kok__09-06-1995.jpg

Land reclamation Check Lap Kok airport Hong Kong

In 1996 Hong Kong was a modern city-state with almost 6 million inhabitants where air traffic was a very important component for economic activity. The old airport Kai Tak, with a single runway, was no longer able to cope with the growing number of passengers and amount of freight.  The authorities decided to build a new, bigger airport at a new location in Hong Kong, a 350 hectares hilly island off the coast about 28 km west of the city center.