Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

The consortium comprising Boskalis, Van Oord, NMDC (Abu Dhabi) and Jan de Nul (Belgium) had the task of dredging the 35 km long New Suez Canal parallel to the existing canal. This involved dredging a record breaking 200 million m3 of sand, clay and rock in less than 9 months. In addition, two Service Channels (80 m wide and design depth -10 m CD) and two Cross Channels (50 m wide and design depth of -6 m CD) were dredged to connect the existing canal and the New Suez Canal.

Enormous scale

Dredging 200 million m3 of material in a period of 9 months required the deployment of the world’s largest dredging fleet comprising 21 Cutter Suction Dredgers, 5 Trailing Suction Hopper Dredgers and 2 Water Injection Dredgers. The dredging vessels cut the capital volume and pumped the mixture of soil and water into 16 disposal basins totaling an area of 73 million m2. This required a total length of 85 km floating and shore pipeline.

Complex planning

To ensure the project was completed on time, the fleet of vessels had to be managed to achieve optimum production levels. The first planning task was to enable as many vessels as possible to dredge simultaneously. This required breaking in at both ends of the New Suez Canal and at four points along the existing canal to create ten fronts for the dredging vessels at an early stage in the project.

Logistics

The project was a major challenge in logistics and could have been a project on its own on managing the logistics of incoming shipments arriving on their own keel, by semi-submersible vessels, cargo vessels, and regular air freight, sea freight and road transport.

Time pressure

The main challenge for the Consortium was the time frame in which all dredging had to be completed. A project of this scale was initially estimated to take three years to complete, but the President of Egypt had set the limit for completion at one year. The period from tender to contract award was only one month, and dredging started within a month. The New Suez Canal was open for shipping in just five days after completion of the dredging works.

Facts and figures

  • 35 km long canal with bottom width 147 to 177 m and design depth -24 m CD
  • 2 Service Channels (width 80 m and design depth -10 m CD), and 2 Cross Channels (width 50 m and design depth -6 m CD)
  • 9 months execution period including preparations
  • 28 dredgers on site including 21 Cutter Suction Dredgers, 5 Trailing Suction Hopper Dredgers and 2 Water Injection Dredgers
  • 85 km soil conveying pipeline (floating and shore pipeline)
  • 16 disposal basins located on the east and west banks of the New Suez Canal
  • Approximately 2,000 people from 45 countries employed on site; over 4.5 million man-hours, over 3,700 project safety inductions, and no fatal injuries or permanent disabilities
  • The New Suez Canal was opened for shipping on 6 August 2015, 5 days after completion of dredging
  • Extension of time was not possible

Related projects

Selected filters
gavle_hamn_201319_DD_Bewerkt_header.jpg

Port extension, Port of Gävle

The Port of Gävle is located on the east coast of Sweden in the Gulf of Bothnia, facilitating Swedish imports and exports. The client wished to improve maritime safety and accessibility, and to increase the throughput of goods in this harbor.

20120229-DSC_3214_header.jpg

Port expansion, Onne

In May 2011 Boskalis was awarded the project for the expansion of the Federal Lighter Terminal and Federal Ocean Terminal of the Onne Port Complex by Prodeco International Limited. The project entails the reclamation of approximately 200 ha with suitable materials from nearby borrow areas.

Boskalis_Genova_VOLO_ph-merlo_110112-3725_header.jpg

Port upgrade, Genoa

The deepening and extension of the port of Genoa is needed to accommodate the larger container vessels and the ferries of MSC. The client is the Port Authority of Genoa. The project is being executed by Boskalis Italia S.r.l. in a joint venture with Tecnis S.p.A., an Italian company that is responsible for the construction work.

B_nieuw_header.jpg

Port and MOF, LNG plant Barrow Island, Gorgon

Design and construction of a new port and materials offloading facility in a class 'A' nature reserve. The project owner is developing LNG process facilities on Barrow Island off the north west coast of Western Australia approximately 140 km west of Dampier and 95 km north east of Onslow. Barrow Island is a Class A Nature Reserve and an internationally important conservation estate.

DSC_5770_header.jpg

Port development, Mombasa

The Port of Mombasa is currently the biggest port on the coast of East Africa north of Durban, and the only international port in Kenya. It is now in the throes of a huge expansion drive to both increase cargo handling capacity and accommodate Panamax and Post Panamax vessels. The port is a transit route for, mainly, Uganda, Rwanda, South Sudan and Northern Tanzania. The current container terminal has an installed capacity of 250,000 TEU but handled more than 770,000 TEU in 2011. The port will raise its profile as a regional hub by building a second container terminal with a capacity of 1.2 million TEU. The port authority decided to construct the container terminal in phases.

_Group_4_-_DSC7015__DSC7024-3_images_header.jpg

Port development, Tanger Med 2

Tanger-Med is a cargo and passenger port located about 40 km east of Tangiers, Morocco, on the Straits of Gibraltar at the crossing of two major maritime routes only 15 km from the European mainland.