To main content

Coastline fixation, Cotonou

The project was developed to arrest coastline erosion in the densely-populated centre of Cotonou caused by two phenomena: erosion and human interference along the West African coastline.

After Contract award, the first production and installation activities began in June 2012. Construction was completed in July 2014. The project scope encompassed the supply of the materials and the construction of seven groins (EPIs), a revetment with an approximate length of 300 meters, and a breakwater. A total of 2,680 meters of groin, revetment or breakwater have been built and 7.5 kilometers of coastline have been fixated. The materials supplied consisted of:

  • 2,441 concrete Xblocs measuring 4 m3
  • 32,000 m2 of geotextile
  • 530,000 tonnes of rock of miscellaneous categories.

Including concrete aggregates, 545,000 tonnes of raw rock material corresponding to 21,750 truckloads was transported to the site, approximately 3,500 tonnes of cement in 137 twenty-foot containers was transported to the site. The Xbloc elements were produced under our own management using in-house expertise. A concrete laboratory was imported and operated by in-house personnel to ensure close quality monitoring and compliance with the specifications. Boskalis staff supervised the quarry operations. The quarries were located approximately 180 kilometers inland. Boskalis was responsible for loading from the stockpiles in the quarries. The installation spread consisted of one Hitachi 1200, three Caterpillar 385s, three wheelloaders Caterpillar 980, two Caterpillar 365s and four Caterpillar 740 dumpers.

Related projects

Selected filters
hires-6917.jpg

Construction motorway, A4 Delft-Schiedam

Boskalis Nederland was involved in the construction of the A4 motorway from Delft to Schiedam. The client is Rijkswaterstaat. After 40 years, the construction of this final section will bring to an end the public debate about whether this new road was needed.

Boskalis_Suezkanaal_cutter_suction_dredgers_4153_header.jpg

Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

DSC_0008_header.jpg

Onshore co-mining project, Lelydorp

Suralco L.L.C., an indirect joint subsidiary of Alcoa Inc. and Alumina Ltd., has awarded Boskalis a contract for the mining of bauxite in Lelydorp, Suriname. Boskalis is responsible for the entire mining process, from engineering and overburden removal to bauxite mining and ore delivery.

Picture_6_header.jpg

Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

P1030713_header.jpg

Dredging and reclamation, Songdo International City

Boskalis has been awarded a contract by Daewoo E&C for the dredging and reclamation of new land for Songdo International City on the waterfront of Incheon, South Korea. The total value of the contract amounts to approximately EUR 80 million.

CIMG1866_header.jpg

Coastline fixation, Cotonou

The project was developed to arrest coastline erosion in the densely-populated centre of Cotonou caused by two phenomena: erosion and human interference along the West African coastline.