Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

Permanent works under the contract which are required to be designed, procured, installed, tested and commissioned include both onshore and offshore block items, along with a range of temporary works e.g. buildings, utilities, roads. The project requires interfacing with the existing systems and other ongoing pipeline projects in the area. Leighton Offshore is responsible for integrating, testing, commissioning and staff training of the ongoing project’s operational personnel and to put the entire pipeline system into service.

Project description

Atlantique Dragage started on the project in December 2012 with dredging of the three trenches by TSHD Oranje. The three trenches have a total length of 21 km and were dredged to a maximum depth of 3.5 m. A total volume of 2 M m3 of soil material was removed from the trenches. This material consisted mostly of silt, clay and sandy material but also cap rock and calcarenite material was encountered in one area of the trench running between the KAOOT and ABOT terminals. This material was pre-treated by having it crushed with the CSD Phoenix. The crushed material was then removed by the Oranje. The trenches were completed within a tight schedule enabling the installation of the pipelines without delays. Another part of the scope was dredging of a turning circle of the SPM. This circle has a radius of 1200 m and was dredged to a depth of 26 m. The inner circle with a radius of 100 m was dredged to create minimum depth of 30 m to allow for the installation of the PLEM (pipeline end manifold) of the SPM. TSHD Oranje dredged 10 M m3 material from the turning circle. The material was disposed in designated disposal area. Dredging of the turning circle was completed in August 2013.

Related projects

Selected filters
TSHD_Barent_Zanen_backfilling_at_Denia_header.jpg

Landfall construction
Balearic submarine pipeline

As part of its network expansion program, Enagas undertook the installation of a submarine pipeline providing natural gas from the Spanish mainland to the Balearic Islands of Ibiza and Mallorca, integrating them into the Spanish gas system. This 20" nominal diameter pipeline was constructed in two distinct sections, one of 123 km between the mainland and Ibiza and another of 146 km between Ibiza and Mallorca.

Baydaratskaya_Bay.jpg

Installation gas pipeline, Baydaratskaya Bay

The Baydaratskaya Bay Project is located in the Kara Sea in the North of Russia. The Kara Sea is bordered on its western side by Novaya Zemlya and on the east by the North Siberian Coast. Baydaratskaya Bay is located in the south of the Kara Sea between the Ural Coast and the Yamal Peninsula. Yamalgasinvest (Gazprom) is planning the construction of four pipelines and two cable crossings at Baydaratskaya Bay for the exploitation of the Bovanenkova and Harasawejskoje gas field on the Yamal Peninsula.

DPFV_Seahorse_moors_for_loading_header.jpg

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

Installation_of_cofferdam_to_enable_trench_excavation_through_surf_zone_header.jpg

Crude oil unloading facilities, Sri Racha

Thai Oil Public Company Limited is the largest petroleum oil refiner and supplier in Thailand. To enable Very Large Crude Carriers (VLCC) up to 320,000 DWT or a freight capacity of up to two million barrels to berth at Thai Oil's refinery in Sri Racha, Chonburi Province, a second Single Buoy Mooring (SBM) facility was installed approximately 14 km offshore, in water depths of around 30 m. From this buoy, a 52' diameter concrete coated steel pipeline had to be installed to the landfall location near the Thai Oil refinery.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.