To main content

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

Permanent works under the contract which are required to be designed, procured, installed, tested and commissioned include both onshore and offshore block items, along with a range of temporary works e.g. buildings, utilities, roads. The project requires interfacing with the existing systems and other ongoing pipeline projects in the area. Leighton Offshore is responsible for integrating, testing, commissioning and staff training of the ongoing project’s operational personnel and to put the entire pipeline system into service.

Project description

Atlantique Dragage started on the project in December 2012 with dredging of the three trenches by TSHD Oranje. The three trenches have a total length of 21 km and were dredged to a maximum depth of 3.5 m. A total volume of 2 M m3 of soil material was removed from the trenches. This material consisted mostly of silt, clay and sandy material but also cap rock and calcarenite material was encountered in one area of the trench running between the KAOOT and ABOT terminals. This material was pre-treated by having it crushed with the CSD Phoenix. The crushed material was then removed by the Oranje. The trenches were completed within a tight schedule enabling the installation of the pipelines without delays. Another part of the scope was dredging of a turning circle of the SPM. This circle has a radius of 1200 m and was dredged to a depth of 26 m. The inner circle with a radius of 100 m was dredged to create minimum depth of 30 m to allow for the installation of the PLEM (pipeline end manifold) of the SPM. TSHD Oranje dredged 10 M m3 material from the turning circle. The material was disposed in designated disposal area. Dredging of the turning circle was completed in August 2013.

Related projects

Selected filters

Installation gas pipeline, Balgzand-Bacton

BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m3 of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.