Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

Project challenges

The main challenges, which were dealt with effectively during project preparation and execution, were:

  • The actual data for the FPSO was known at a very late stage of the project, considerably reducing the time available for the engineering phase;
  • The hull of the FPSO was stiffer than the hull of the DWV. This difference in the deflection characteristics of the two vessels resulted in high peak loads on the forward and aft ends of the cribbing wood and the FPSO hull when a sagging wave was introduced in the design phase. It was a huge engineering challenge to determine the best cribbing layout within a very short time. In the end, the cribbing beams at the bow and stern were reduced in height (by up to -40 mm) to manage the high peak loads exerted on the FPSO structure;
  • The water at the loading location was not deep enough to load the FPSO safely. A few days prior to loading, half a meter silt was dredged from the seabed to provide an underkeel clearance of 0.5 m during the submerging operation;
  • Access to the discharge location was a challenge in itself because of the shallow patches and wrecks in the approach channel. Good seamanship of the vessel’s crew, in combination with additional detailed navigational charts of the area and the early boarding of the pilot, ensured that the DWV arrived safely at the discharge location.

Conclusion

The Armada Intrepid FPSO was transported successfully from Rotterdam (Netherlands) to Batam (Indonesia). Dockwise provided the required service in time to the Client, dealing with all the given engineering and operational challenges. Evaluating the project preparation and execution, it can be concluded that a combination of operational best practices and engineering analysis was decisive for the safe, controlled and successful execution of the project.

Related projects

Selected filters
TSHD_Barent_Zanen_backfilling_at_Denia_header.jpg

Landfall construction
Balearic submarine pipeline

As part of its network expansion program, Enagas undertook the installation of a submarine pipeline providing natural gas from the Spanish mainland to the Balearic Islands of Ibiza and Mallorca, integrating them into the Spanish gas system. This 20" nominal diameter pipeline was constructed in two distinct sections, one of 123 km between the mainland and Ibiza and another of 146 km between Ibiza and Mallorca.

Baydaratskaya_Bay.jpg

Installation gas pipeline, Baydaratskaya Bay

The Baydaratskaya Bay Project is located in the Kara Sea in the North of Russia. The Kara Sea is bordered on its western side by Novaya Zemlya and on the east by the North Siberian Coast. Baydaratskaya Bay is located in the south of the Kara Sea between the Ural Coast and the Yamal Peninsula. Yamalgasinvest (Gazprom) is planning the construction of four pipelines and two cable crossings at Baydaratskaya Bay for the exploitation of the Bovanenkova and Harasawejskoje gas field on the Yamal Peninsula.

DPFV_Seahorse_moors_for_loading_header.jpg

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

Installation_of_cofferdam_to_enable_trench_excavation_through_surf_zone_header.jpg

Crude oil unloading facilities, Sri Racha

Thai Oil Public Company Limited is the largest petroleum oil refiner and supplier in Thailand. To enable Very Large Crude Carriers (VLCC) up to 320,000 DWT or a freight capacity of up to two million barrels to berth at Thai Oil's refinery in Sri Racha, Chonburi Province, a second Single Buoy Mooring (SBM) facility was installed approximately 14 km offshore, in water depths of around 30 m. From this buoy, a 52' diameter concrete coated steel pipeline had to be installed to the landfall location near the Thai Oil refinery.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.