To main content

Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

Project challenges

The main challenges, which were dealt with effectively during project preparation and execution, were:

  • The actual data for the FPSO was known at a very late stage of the project, considerably reducing the time available for the engineering phase;
  • The hull of the FPSO was stiffer than the hull of the DWV. This difference in the deflection characteristics of the two vessels resulted in high peak loads on the forward and aft ends of the cribbing wood and the FPSO hull when a sagging wave was introduced in the design phase. It was a huge engineering challenge to determine the best cribbing layout within a very short time. In the end, the cribbing beams at the bow and stern were reduced in height (by up to -40 mm) to manage the high peak loads exerted on the FPSO structure;
  • The water at the loading location was not deep enough to load the FPSO safely. A few days prior to loading, half a meter silt was dredged from the seabed to provide an underkeel clearance of 0.5 m during the submerging operation;
  • Access to the discharge location was a challenge in itself because of the shallow patches and wrecks in the approach channel. Good seamanship of the vessel’s crew, in combination with additional detailed navigational charts of the area and the early boarding of the pilot, ensured that the DWV arrived safely at the discharge location.

Conclusion

The Armada Intrepid FPSO was transported successfully from Rotterdam (Netherlands) to Batam (Indonesia). Dockwise provided the required service in time to the Client, dealing with all the given engineering and operational challenges. Evaluating the project preparation and execution, it can be concluded that a combination of operational best practices and engineering analysis was decisive for the safe, controlled and successful execution of the project.

Related projects

Selected filters
Seahorse_-_Nord_Stream_2032010_header.jpg

Trench dredging gas pipeline, Nord Stream

The Nord Stream gas pipeline project is a joint project of four major companies: Gazprom, BASF/Wintershall, E.ON Ruhrgas and Gasunie. The project is more than just a pipeline. It is a new channel for Russian natural gas exports and a major infrastructure project which is expected to set a new benchmark in EU-Russia cooperation. In view of current developments the new pipeline will be an important factor of energy security in Europe.

D1107-1233_header.jpg

Seabed preparatory works,
Dana Medway

Dana Petroleum Netherlands B.V. is the operator of the Pllb De Ruyter field and oil-producing platform located in the Dutch section of the North Sea.

DPFV_Sandpiper_accompagnied_by_SMIT_tugs_on_her_way__to_worksite_header.jpg

Rock installation, PDET

In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

Belwind_1_bewerkt_header.jpg

Construction wind farm, Belwind

SMIT sheerlegs Taklift 4 installed the final element for one of Belgium’s first offshore wind farms, Belwind, the wind farm’s high voltage transformer substation. SMIT also provided the transport of the element and other marine support services to assist the construction of the wind farm.

Walney_wind_farm_UK_support_installatie_monopiles_windmolens_header.jpg

Offshore wind farm, Walney

Windfarm construction projects regularly feature in the work programmes of SMIT’s sheerlegs fleet. For example, the Taklift 7 was involved in the Walney Offshore Windfarm development in the Irish Sea. Walney Offshore is a wind farm project developed by DONG in the Irish Sea, some 20 miles from the coast at Barrow.

Magellan_4_header.jpg

Pipeline crossing, Strait of Magellan

The project involved the construction of a new, strategically important, 24" natural gas pipeline across the Strait of Magellan, linking Cabo Espíritu Santo in Tierra del Fuego province with Cabo Vírgenes in Santa Cruz province. The new pipeline was built as an expansion of the existing San Martín pipeline in an effort by the government to increase gas supplies from Tierra del Fuego to the Argentinian mainland.