Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

The early works

In October 2007 Brass LNG awarded Nigerian Westminster Dredging & Marine Limited (NWDM) the Early Works EPC Contract. The project consisted of the construction of a Pioneer Camp and three Pre-Loads to provide early settlement for the future tank farm of the proposed Brass LNG plant. In more detail the Scope of Work consisted of bush clearing and topsoil removal, the construction of temporary roads and pipeline crossings, the excavation of sand for the construction of the pre-loads, installation of vertical drains, the installation of settlement monitoring instrumentation and the monitoring thereof and covering the completed pre-loads with poly sheets.
The Pioneer Camp was designed to be fully self-supporting. Apart from accommodation units it consists of offices, catering, laundry and water treatment facilities. For the power supply three generators were supplied and installed. Furthermore, provisions were made for waste water and sewage treatment and for waste disposal an incinerator was supplied and installed. 

Execution

The bush clearing was mainly sub-contracted to local contractors from the three host communities. Immediately upon having the first areas cleared, sand excavation started to construct the temporary roads, and to create dry and stable platforms for the construction of the accommodation and offices, and for the pre-loads.
Approximately 1,5 million m3 of sand was excavated and transported for the construction of the three pre-loads, which were elevated to  approximately 20 meter height. The required sand was excavated from an onshore borrow area. Over 30 heavy duty dry earth moving machines were brought to site to execute the works, such as excavators, bulldozers, vibro roller compactors, articulated dump trucks, etc.

Related projects

Selected filters
P67.jpg

P67 FPSO Transportation

On behalf of Company Petrobras and Client COOEC, Boskalis executed the dry transportation of the P-67 FPSO in 2018 from the COOEC Qingdao yard in China to Rio de Janeiro in Brazil. The P-67 FPSO will produce 150,000 bpd and compress six million cubic meters of natural gas daily in the Lula North section of the Lula-Cernambi field in the Santos basin.

Pluit_City_Island-bird_eye_view.jpg

Artificial island
off the coast of
Jakarta, Indonesia

Boskalis has been awarded a contract by PT Muara Wisesa Samudra to design and construct an artificial island measuring 160 hectares off the coast of Jakarta, Indonesia. The work is part of the dredging and land development works for the new Pluit City. It will be executed in a joint venture with Van Oord.

Harderwijk_Lorentzhaven__7__header.jpg

Redevelopment Waterfront, Harderwijk

Boskalis Nederland is involved in one of the largest redevelopment projects in the Netherlands. The Harderwijk Waterfront project involves the complete transformation of the lakeside area of this IJsselmeer town. The project covers a strip approximately six kilometers long, combining homes, work and recreation in a natural way. The Harderwijk Waterfront will generate a quality boost in many areas: quality of life, employment, traffic, tourism and the environment.

Medium-Foto_1_-_artist_impression_nw_situatie_A1_afslag_met_spoorbrug__1_.jpg

Road enlargement motorway A1-A6, Diemen-Almere

The A1/A6 project is one of the five sub-projects for Rijkswaterstaat that are included in the upgrading of the road network linking Schiphol Airport, Amsterdam, and Almere (SAA). The total length of the SAA link is 40 kilometers. Boskalis, together with partners, is responsible for the section from the Diemen intersection to Almere, a distance of approximately 23 kilometers.

29-8-11_006_header.jpg

Port maintenance,
Açu Port

Açu Port in São João da Barra, Rio de Janeiro (Brazil) is one of the largest port-industry complex in Latin America. The port consists of two terminals: T1, an offshore terminal for handling iron ore and oil, and T2, an onshore terminal built around the inner navigation channel which accommodates offshore supply companies and will handle bauxite, general cargo and vehicles.

Shell Malikai

Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell Petroleum Company is the designated Operator. A floating Dry Tree Unit (DTU) will be installed over Malikai field utilizing a Tension Leg Platform (TLP) design that suits the Malikai environment.