Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

The early works

In October 2007 Brass LNG awarded Nigerian Westminster Dredging & Marine Limited (NWDM) the Early Works EPC Contract. The project consisted of the construction of a Pioneer Camp and three Pre-Loads to provide early settlement for the future tank farm of the proposed Brass LNG plant. In more detail the Scope of Work consisted of bush clearing and topsoil removal, the construction of temporary roads and pipeline crossings, the excavation of sand for the construction of the pre-loads, installation of vertical drains, the installation of settlement monitoring instrumentation and the monitoring thereof and covering the completed pre-loads with poly sheets.
The Pioneer Camp was designed to be fully self-supporting. Apart from accommodation units it consists of offices, catering, laundry and water treatment facilities. For the power supply three generators were supplied and installed. Furthermore, provisions were made for waste water and sewage treatment and for waste disposal an incinerator was supplied and installed. 

Execution

The bush clearing was mainly sub-contracted to local contractors from the three host communities. Immediately upon having the first areas cleared, sand excavation started to construct the temporary roads, and to create dry and stable platforms for the construction of the accommodation and offices, and for the pre-loads.
Approximately 1,5 million m3 of sand was excavated and transported for the construction of the three pre-loads, which were elevated to  approximately 20 meter height. The required sand was excavated from an onshore borrow area. Over 30 heavy duty dry earth moving machines were brought to site to execute the works, such as excavators, bulldozers, vibro roller compactors, articulated dump trucks, etc.

Related projects

Selected filters
Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.

hires-6917.jpg

Construction motorway, A4 Delft-Schiedam

Boskalis Nederland was involved in the construction of the A4 motorway from Delft to Schiedam. The client is Rijkswaterstaat. After 40 years, the construction of this final section will bring to an end the public debate about whether this new road was needed.

Boskalis_Suezkanaal_cutter_suction_dredgers_4153_header.jpg

Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

DSC_0008_header.jpg

Onshore co-mining project, Lelydorp

Suralco L.L.C., an indirect joint subsidiary of Alcoa Inc. and Alumina Ltd., has awarded Boskalis a contract for the mining of bauxite in Lelydorp, Suriname. Boskalis is responsible for the entire mining process, from engineering and overburden removal to bauxite mining and ore delivery.

Picture_6_header.jpg

Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

P1030713_header.jpg

Dredging and reclamation, Songdo International City

Boskalis has been awarded a contract by Daewoo E&C for the dredging and reclamation of new land for Songdo International City on the waterfront of Incheon, South Korea. The total value of the contract amounts to approximately EUR 80 million.