Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

The early works

In October 2007 Brass LNG awarded Nigerian Westminster Dredging & Marine Limited (NWDM) the Early Works EPC Contract. The project consisted of the construction of a Pioneer Camp and three Pre-Loads to provide early settlement for the future tank farm of the proposed Brass LNG plant. In more detail the Scope of Work consisted of bush clearing and topsoil removal, the construction of temporary roads and pipeline crossings, the excavation of sand for the construction of the pre-loads, installation of vertical drains, the installation of settlement monitoring instrumentation and the monitoring thereof and covering the completed pre-loads with poly sheets.
The Pioneer Camp was designed to be fully self-supporting. Apart from accommodation units it consists of offices, catering, laundry and water treatment facilities. For the power supply three generators were supplied and installed. Furthermore, provisions were made for waste water and sewage treatment and for waste disposal an incinerator was supplied and installed. 

Execution

The bush clearing was mainly sub-contracted to local contractors from the three host communities. Immediately upon having the first areas cleared, sand excavation started to construct the temporary roads, and to create dry and stable platforms for the construction of the accommodation and offices, and for the pre-loads.
Approximately 1,5 million m3 of sand was excavated and transported for the construction of the three pre-loads, which were elevated to  approximately 20 meter height. The required sand was excavated from an onshore borrow area. Over 30 heavy duty dry earth moving machines were brought to site to execute the works, such as excavators, bulldozers, vibro roller compactors, articulated dump trucks, etc.

Related projects

Selected filters
_Group_4_-_DSC7015__DSC7024-3_images_header.jpg

Port development, Tanger Med 2

Tanger-Med is a cargo and passenger port located about 40 km east of Tangiers, Morocco, on the Straits of Gibraltar at the crossing of two major maritime routes only 15 km from the European mainland.

TSHD_Cornelis_Zanen_rainbowing_header.jpg

Port upgrade, Pointe Noire

The rehabilitation of the Port of Pointe-Noire focused on the renovation and upgrading of the main infrastructure of the port and its adaptation to developments in containerized traffic, offering a draught of -15 m. Furthermore, the work included the construction of a protective berm, an extension of the external breakwater, the rehabilitation and extension of quays, and dredging work.

DSC_0602_header.jpg

Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

19DS9430_12-11-26_005_header.jpg

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

Aeroview_D1207-944_header.jpg

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

Gbaran_Ubie_filter_placement_header.jpg

Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.