To main content

IJsseldelta

The IJsseldelta project is part of the national Room for the River program, which comprises over 30 measures aimed at upgrading the flood defenses in the Dutch river areas. The project involves lowering the summer bed of the Lower IJssel river along a length of 7.5 kilometers near the town of Kampen and creating a bypass to the south of Kampen.

Isala Delta

Boskalis Nederland is executing the work in conjunction with Van Hattum and Blankevoort in the Isala Delta building consortium, which was awarded the Design & Construct contract by the Dutch Department of Public Works and the province of Overijssel. In addition to normal procedures the tendering process involved so-called competition-oriented dialogue. This special procedure involves conducting dialogue beforehand with the prospective contractors, giving Isala Delta a better understanding of what the clients wanted and giving the commissioning bodies a better idea of both the potential solution options and the project risks.

Work

The project consists of two measures to guarantee the future protection of the Kampen-Zwolle region against flooding: firstly the lowering of the summer bed of the Lower IJssel, involving the deepening of the river along a length of 7.5 kilometers between the Molenbrug and Eilandbrug bridges, and secondly the realization of the Reevediep, a new side branch of the River IJssel to the south of Kampen, towards the Drontermeer lake. This will also enhance the rural planning quality of the surrounding area. The natural flood protection in three flood plains will be reinforced. Over 300 hectares of new delta nature area will be realized in the Reevediep, including new walking and hiking paths and cycle tracks, and we are also creating a special channel for pleasure craft. As part of the Reevediep project Isala Delta will also realize an intake pipeline, a lock for pleasure craft, a bridge and two turning locks.

Planning schedule

Initial preparations started in the fall of 2014. Dredging work will commence in mid-2015, with the project becoming increasingly visible from then on. Under the current schedule the project to lower the summer bed will be completed by the end of 2016. We expect to deliver the entire project (stage 1) by the end of 2019.

Related projects

Selected filters
DSC04359_header.jpg

Port access channel dredging, Walvis Bay

The port of Walvis Bay is a naturally sheltered deepwater harbor on the west coast of Africa. The port is part of a transit route linking Southern Africa, Europe and the Americas and it is Namibia’s largest commercial port, handling around 5 million tons of cargo each year. The container terminal can accommodate a throughput of about 250,000 containers per year.

IMG_8772_header.jpg

Coastal protection, St. Petersburg

St. Petersburg is a UNESCO World Heritage City, but its location along the River Neva means that it has been threatened by over 300 floods since its founding by Peter the Great in 1703. The completion of the new 25 km long storm-surge barrier across the Gulf of Finland ensures that the city will no longer be vulnerable to high tides and devastating floods. As a result of the new Flood Protection Barrier, however, the old winding access channel had to be replaced with a new, straighter, more easily navigable channel.

Delflandse_coast___3__header.jpg

Coastal protection, Delfland coast

In August 2008 Van Oord and Royal Boskalis Westminster N.V. have been awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce a weak link in the Delflandse coast . The contract is worth EUR 120 million of which Van Oord and Boskalis have an equal share.

IMG_1888_header.jpg

Cleanup, Zellingwijk area

The Zellingwijk quarter of the village of Gouderak was built in the middle of the last century. In the early 1980s it became clear that the soil underneath this residential area was heavily contaminated as a result of the dumping of waste - mainly mineral oils and pesticides. The homes built on the site were subsequently demolished in the mid-1980s. Pending definitive remediation work, a layer of concrete / asphalt was applied to seal the site.

DSCF0279_header.jpg

Overview activities, Bahrain

The Kingdom of Bahrain is an island located in the Gulf, east of Saudi Arabia and north of Qatar and connected with its neighbour Saudi Arabia since the year 1980 with a 25 km long causeway. The archipelago consists of some 30 islands with a total of 160 km of shoreline and has a population of 800,000. Whereas the surface of Bahrain in the year 1960 was around 650 km2, the last decennia have seen a steady increase in the surface till a respectable figure of 740 km2 in 2007. This increase has been achieved by a various number of small and mayor reclamation projects.

37ac96e429c252fd55f1136ce6374c9e_image_header.jpg

Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.