IJsseldelta

The IJsseldelta project is part of the national Room for the River program, which comprises over 30 measures aimed at upgrading the flood defenses in the Dutch river areas. The project involves lowering the summer bed of the Lower IJssel river along a length of 7.5 kilometers near the town of Kampen and creating a bypass to the south of Kampen.

Isala Delta

Boskalis Nederland is executing the work in conjunction with Van Hattum and Blankevoort in the Isala Delta building consortium, which was awarded the Design & Construct contract by the Dutch Department of Public Works and the province of Overijssel. In addition to normal procedures the tendering process involved so-called competition-oriented dialogue. This special procedure involves conducting dialogue beforehand with the prospective contractors, giving Isala Delta a better understanding of what the clients wanted and giving the commissioning bodies a better idea of both the potential solution options and the project risks.

Work

The project consists of two measures to guarantee the future protection of the Kampen-Zwolle region against flooding: firstly the lowering of the summer bed of the Lower IJssel, involving the deepening of the river along a length of 7.5 kilometers between the Molenbrug and Eilandbrug bridges, and secondly the realization of the Reevediep, a new side branch of the River IJssel to the south of Kampen, towards the Drontermeer lake. This will also enhance the rural planning quality of the surrounding area. The natural flood protection in three flood plains will be reinforced. Over 300 hectares of new delta nature area will be realized in the Reevediep, including new walking and hiking paths and cycle tracks, and we are also creating a special channel for pleasure craft. As part of the Reevediep project Isala Delta will also realize an intake pipeline, a lock for pleasure craft, a bridge and two turning locks.

Planning schedule

Initial preparations started in the fall of 2014. Dredging work will commence in mid-2015, with the project becoming increasingly visible from then on. Under the current schedule the project to lower the summer bed will be completed by the end of 2016. We expect to deliver the entire project (stage 1) by the end of 2019.

Related projects

Selected filters
hfd_onder_header.jpg

Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

Balboa_2_header.jpg

Port expansion, Balboa

The plans to expand the Panama Canal represent one of the most important infrastructure improvements of the 21st century. Since its opening in 1913 the Canal has provided the shortest and most economically viable shipping route from Pacific to Atlantic seaports. With the ever-increasing size of modern-day vessels, it was inevitable that the Canal would need to be widened and deepened. The expansion of the Canal has made the extension of the Port of Balboa at the mouth of the canal on the Pacific Ocean a necessity. The Phase 4 projects included Marine Works and Civil Works to improve two existing berths and to build a completely new berth capable of handling not only Post Panamax but also Super Post Panamax ships.

DSCF0226_header.jpg

Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

Figure_1_header.jpg

Port environmental mitigation measures, Hamina

Hamina, which is close to the Russian border in south-east Finland, is a home port for the oil industry and a transit harbor for timber, cars and other goods on their way to Russia. To provide access for larger vessels it had to deepen the existing channel by two meters to 12 meters and create a new channel section. Terramare Oy, a subsidiary of Royal Boskalis Westminster, won this assignment in late 2008. The project started in July 2009.

Raahe_1_header.jpg

Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.

_L4F8705_header.jpg

Port development, Pipavav

As a result of the booming container market in recent years, GPPL and APM Terminals introduced a long term investment plan to further develop the port’s facilities. Phase 2 of the expansion program included the reclamation of a new storage (container stacking) area and the extension of the port’s capacity by deepening the approach, channels and berths, allowing larger (container) vessels to enter the port. Zinkcon Marine Singapore, a subsidiary of Boskalis International B.V., won the contract for the dredging and reclamation works for Phase 2. In the beginning of 2009, however, the client re-evaluated the investment against the background of the dramatic effects of the economic crisis, which seriously affected the global container market. GPPL, APMT and ZMS agreed to optimize the project in such a way that all parties would benefit.