Port development, Pipavav

As a result of the booming container market in recent years, GPPL and APM Terminals introduced a long term investment plan to further develop the port’s facilities. Phase 2 of the expansion program included the reclamation of a new storage (container stacking) area and the extension of the port’s capacity by deepening the approach, channels and berths, allowing larger (container) vessels to enter the port. Zinkcon Marine Singapore, a subsidiary of Boskalis International B.V., won the contract for the dredging and reclamation works for Phase 2. In the beginning of 2009, however, the client re-evaluated the investment against the background of the dramatic effects of the economic crisis, which seriously affected the global container market. GPPL, APMT and ZMS agreed to optimize the project in such a way that all parties would benefit.

Although Pipavav is a sheltered port, the working season for dredging and reclamation activities is limited to the period October - May. During the monsoon season, numerous gails, heavy rain periods, strong currents and occasional swell hamper the process of dredging. Demobilisation by towing can be particularly hazardous. This situation called for a tight time frame. After the contract was signed in October 2008, mobilization activities started in November / December 2008. Consequently, the actual dredging work commenced in early January 2009, when the Cutter Suction Dredger Cyrus II was employed for the dredging of a volume of 1,900,000 m3. The dredged material, mainly consisting of sandstone and a mixture of sand and clay, was pumped ashore into the reclamation area. In May 2009, the Trailing Suction Hopper Dredger Prins der Nederlanden dredged the outer channel. A total volume of 400,000 m3 was dumped offshore. The project was completed by the end of May, well before the start of the monsoon.

Related projects

Selected filters
Marker_Wadden_spread_def_1920.jpg

Construction of
Marker Wadden

Boskalis has been awarded the first phase of the Marker Wadden development in the Netherlands. The project includes the construction of an island with underwater landscaping. The Marker Wadden are natural islands that will be developed in the Markermeer lake in the years to come. They will provide a major boost for the ecological quality of the Markermeer lake. The natural shores of the islands will give fish more opportunities to spawn and feed. As a result, large numbers of birds such as terns and waders will return to the area because there will be more food for them. The construction of the Marker Wadden will transform the map of the Netherlands.

Adelaide.png

Outer harbor channel widening, Adelaide.

The Port of Adelaide is the primary port in South Australia, located at Outer Harbor. The port is operated by Flinders Ports Pty Ltd (Flinders Ports) and handles both container and cruise vessels, contributing significantly to the State’s economic activity. Flinders Ports identified the need for an upgrade of the existing infrastructure driven by the emergence of Post Panamax class vessels. To meet this growth the existing channel had to be widened to accommodate vessels with a maximum width of 49 m without operational restrictions. Flinders Ports contracted Boskalis to execute the dredging works.

Medium-FF95893.jpg

Johan Sverdrup, transport.

Samsung Heavy Industries Co., Ltd. is Equinor’s Fabrication and Transport contractor of the Johan Sverdrup project. Boskalis has been awarded by Samsung as transportation contractor for this project.

DSC_0204_header.jpg

IJsseldelta

The IJsseldelta project is part of the national Room for the River program, which comprises over 30 measures aimed at upgrading the flood defenses in the Dutch river areas. The project involves lowering the summer bed of the Lower IJssel river along a length of 7.5 kilometers near the town of Kampen and creating a bypass to the south of Kampen.

union_bear_and_pricess.jpg

NORDSTREAM II

Allseas Engineering had been awarded with the contract to support partly with construction of the offshore natural gas transmission system comprising two 48” diameter pipelines from Russia to the Baltic through Germany (NPSP2). The installation of the NSP2 pipeline has been performed by Charterers pipelay vessels: Solitaire, Pioneering Spirit and Audacia.

Port expansion, Tuas Mega Port Singapore

Boskalis is part of a consortium that won a contract related to the construction of the Tuas Mega Port in Singapore. After Shanghai, Singapore is not only the world's largest container port, it also handles 50% of global crude oil production and it is the planet's busiest transit port. The port is the economic motor of Singapore, which is constantly struggling with a shortage of land.