BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m<sup>3</sup> of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

The scope started at the tie-in to the HDD dune crossing on the beach. Planning of activities on the beach required careful consideration with regard to the sensitive dune areas adjacent to the project site and tourists on the beach during the summer season. From the beach a 300 meters long sheet piled cofferdam was installed to facilitate trench excavation through the surf zone. From the offshore end of the cofferdam a trench was dredged up to 7 kilometers offshore. This scope also included the supply and operation of a 500 tons capacity linear pull winch and pull wire installation to facilitate the beach pull operations. Upon completion of the pipeline installation, the trench was backfilled, the cofferdam removed and the beach re-instated.

Related projects

Selected filters
Ineos_IRM_2018.jpg

Ineos IRM 2018

Boskalis Subsea Services was contracted by INEOS E&P A/S for the 2018 Inspection, Repair and Maintenance (IRM) campaign, involving the preparation and execution of 20-off scopes on various assets.

Haven.jpeg

Haven Jack-up upgrade

The Master Marine accommodation unit HAVEN required an upgrade for operations at the Johan Sverdrup Field.

Oman.jpg

DNO Oman block 8 LTD

DNO Oman Block 8 Ltd (DNO) is the operator of the Bukha Field, offshore Khasab, Oman. DNO entered Oman in 2012 and operates the country's only producing offshore fields on behalf of Omani Oil & Gas ministry. Boskalis Subsea Services (BSS) in recent years have assisted DNO with lifting a flare boom onto the WB Platform, making use of a DP2 offshore vessel, also Boskalis provided diving and inspection services to DNO for their SPM Offshore RAK, UAE.

Offshore_energy_heavy_transport_Dockwise_Vanguard_Aasta_Hansteen.jpg

Transport and installation Aasta Hansteen
spar platform

For the Statoil Aasta Hansteen project, Dockwise has transported the newbuild spar hull from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Høylandsbygd, Norway. The spar is the world’s largest spar ever built to date. 

Offshore_windfarm_heavy_transport_installation_wikinger.jpg

Transport and installation turbine foundations offshore wind farm, Wikinger

The Wikinger offshore wind farm has been developed by Iberdrola in the Baltic Sea area, within the German Exclusive Economic Zone (EEZ). The offshore site is about 34 km northeast of the island of Rügen, and covers an area of roughly 50 km², within which 70 wind turbine generators (WTG) of 5 MW and one offshore substation (OSS) are being installed. The water depths for installation range between 36 and 42 meters. When completed the windfarm will deliver 350 MW electrical power to the German national grid. The transport and installation of the 70 WTG foundations and the piles for the OSS has been carried out by Boskalis.

069dd04102016OWF-_c_Kloet.jpg

Offshore wind farm
monopile installation,
Veja Mate

Boskalis is close to completing one of its latest and most significant offshore wind projects - Veja Mate, in the German North Sea. The project involves handling and installing the biggest monopiles in the industry – weighing between 1,230-1,302-tonne a piece – using the biggest pile gripper frame and pile driving hammers in the industry with a brand new vessel, which also happens to be the biggest in the sector. Once complete, the offshore wind farm will produce over 1,6 TWh of green, renewable electricity annually.