Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

The Santa Maria island is named after one of the vessels used by Christopher Colombus on his first transatlantic voyage in 1492. The island is connected to the shore by a bridge. The project was initiated by the Ocean Reef Island Inc., and Boskalis Panama S.A. was awarded the Design and Construct contract at the end of a tender procedure. The decisive factors included not only the price but also, and more importantly, the reliability of the contractor in terms of quality, the involvement of local management, the proposed construction method, equipment resources, and in-house engineering capability and capacity. After completing two pre-contracts (the construction of a promotional island and the partial removal of soft sediments), the main contract was finally signed on 7 January 2011.

The construction of the island

The first step in the project was the dredging and disposal of the soft sediments overlaying the weathered rock layer with the clamshell Alex and TSHD Flevo. Work then started on the construction of the rock dike. The rock was produced by the Client in the area of Vacamonte and then taken by truck to the Boskalis loading facility alongside the port of Vacamonte. Prior to the start of the contract the Client and Boskalis undertook a detailed soil investigation in the (rock)quarry area in order to establish the presence of the various required gradings. Also during the quarry activities Boskalis supported the Client in order to achieve an optimal quarry performance. The loading facility is in a location that is not sheltered against the long pacific swells. Adopting a flexible loading structure reduced downtime and Boskalis was able to match rock production output without difficulty. A total of five different types of rock grading were used to work as cost-effectively as possible while maintaining the stability of the island given the long and strong swells. The inside of the rock dike was covered with a geotextile to prevent the loss of sand through the dike back into the ocean. By April 2012, the island was ready for filling with sand.

Related projects

Selected filters
2005-09-16-124619-9920_header.jpg

Dredging of sediments, Miami river

The Miami River, which flows through an urban industrial area of Miami, Florida, had not been dredged since the area was built in 1934. In 1990 the US Army Corps of Engineers advised the city that the sediment had to be removed from the river as it was impeding shipping. There was one caveat however: the sediment, contaminated with heavy metals, pesticides and oil, could not be placed in the ocean.

klein_1_header.jpg

Gas fields development, Krishna Godavari basin

A large-scale dredging, trenching, pipe pulling and backfilling project. Reliance Industries develops the offshore gas field known as Block KGDWN-98/3 in the Krishna Godavari Basin, Bay of Bengal off the East Coast of India. The gas field will be linked to onshore customers and covers an area of approximately 7,500 km2. The field stretches an area 40 to 60 kilometers southeast of Kakinada. The scope of works comprised the dredging of a 21 kilometers long and 18 meters wide trench for three 24" gas pipelines, each with a 6" piggyback pipeline, one 12" effluent pipeline and two umbilical cables in water depths ranging from 0 to 50 meters. After pipe laying by the main contractor the pipeline trench was backfilled with partly rock and sand.

Rehabilitation of old breakwater, Port of Poti

The city of Poti is located at the mouth of Georgia’s largest river, the Rioni. It has been an important trade centre for centuries. Since the early 19th century, many plans have been developed for the creation of a major sea port. Construction work started in the 1850s on the main breakwater that is still protecting the port today. During its long lifetime, this structure has been maintained by frequently adding 20-60 tons of concrete cubes to the armour layer. Significant settlement of the structure over time has lowered the crest level considerably, resulting in large overtopping volumes and therefore in port-operation downtime. As a result, a rehabilitation project was executed between 2006 and 2008 by Royal Boskalis Westminster N.V. to reduce the downtime caused by overtopping waves.

Sepetiba_aerial_header.jpg

Reclamation and dewatering works, Sepetiba Bay

The German steel-maker ThyssenKrupp Steel and the Brazilian mining giant Companhia Vale do Rio Doce (CVRD) teamed up to construct a EUR 3 billion steel factory at Sepetiba. This is a small town of 36,000 inhabitants near Rio de Janeiro with good access to the Atlantic Ocean. The new steel factory allowed Brazil not only to export more of its plentiful mineral resources, but also to produce semi-finished products that can be sold at higher margins. The government authorities of Brazil and Rio de Janeiro both supported the project.

SBS_Reclamation_23-05-08_60_header.jpg

Port development, Lerwick

The Port of Lerwick is situated on the east coast of the Shetland Islands, and is operated by Lerwick Port Authority. The 2008 dredging and reclamation works were one of the largest marine projects to be carried out in Scotland in recent years and constituted the largest single investment in the port to date.

vuosaari_1_header.jpg

Port construction, Vuosaari

Vuosaari Harbor is the most significant harbor project in Finnish history; in fact, it is unique even on a European scale. Both existing harbors in Helsinki’s city centre are being transferred to the eastern outskirts of the city. They are being replaced with a harbor with excellent traffic connections that can meet the increasing demand for cargo handling. The Vuosaari Harbor Center will provide a competitive and modern service package, with smooth connections between harbor operations and other logistical facilities. The harbor center will comprise the gate area, the closed harbor area and the adjacent Business Parks. The fairway to the Harbor Center will be 32 km long, at least 200 m wide, and 11 m deep. The port area comprises 150 ha, of which 90 ha will be land reclaimed from the sea.