Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

The Santa Maria island is named after one of the vessels used by Christopher Colombus on his first transatlantic voyage in 1492. The island is connected to the shore by a bridge. The project was initiated by the Ocean Reef Island Inc., and Boskalis Panama S.A. was awarded the Design and Construct contract at the end of a tender procedure. The decisive factors included not only the price but also, and more importantly, the reliability of the contractor in terms of quality, the involvement of local management, the proposed construction method, equipment resources, and in-house engineering capability and capacity. After completing two pre-contracts (the construction of a promotional island and the partial removal of soft sediments), the main contract was finally signed on 7 January 2011.

The construction of the island

The first step in the project was the dredging and disposal of the soft sediments overlaying the weathered rock layer with the clamshell Alex and TSHD Flevo. Work then started on the construction of the rock dike. The rock was produced by the Client in the area of Vacamonte and then taken by truck to the Boskalis loading facility alongside the port of Vacamonte. Prior to the start of the contract the Client and Boskalis undertook a detailed soil investigation in the (rock)quarry area in order to establish the presence of the various required gradings. Also during the quarry activities Boskalis supported the Client in order to achieve an optimal quarry performance. The loading facility is in a location that is not sheltered against the long pacific swells. Adopting a flexible loading structure reduced downtime and Boskalis was able to match rock production output without difficulty. A total of five different types of rock grading were used to work as cost-effectively as possible while maintaining the stability of the island given the long and strong swells. The inside of the rock dike was covered with a geotextile to prevent the loss of sand through the dike back into the ocean. By April 2012, the island was ready for filling with sand.

Related projects

Selected filters
8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.

IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.