To main content

Mooring replacement phase 2, Zafiro Producer

Mobil Equatorial Guinea Incorporated, an affiliate of ExxonMobil, entered into a contract with Boskalis for the Zafiro Producer Mooring Replacement Project Phase 2. The Zafiro Producer is installed in 180 m (590 ft)water depth approximately 74 km (40 nauticalmiles) west of Malabo, Equatorial Guinea.

The Zafiro oil field is located in the 500,000-acre Block B, 68 km (42 miles) WNW of Bioko island, Equatorial Guinea, adjacent to the international border with Nigeria. Water depths range from less than 300 ft to greater than 5,000 ft. The Zafiro-1 discovery well was drilled in February 1995, testing at 10,400 barrels per day (b/d). Three subsequent wells showed the reservoir to be relatively shallow (around 5,000 ft), and low pressure, with a bottom-hole shut-in pressure of 2,800 psig. The Zafiro Producer is a converted 268,191 dwt VLCC (very large crude carrier). The tanker was built in 1973, with an overall length of 331.5 m, a breadth of 56 m and a depth of 26.4 m. It has a draught of 20.5 m fully loaded, or 8.3 m ballasted. Early reservoir evaluation indicated that a 40,000 b/d rate could be expected from the planned eight wells, requiring the installation of an 80,000 b/d process plant, a 40 MMSCFD gas flare capacity and storage for 1.7 MMBBL of oil.The FPSO was installed in 1996 and later the storage capacity was taken over by the Serpentina changing the Zafiro Producer into a FPU (Floating Production Unit).

Mooring replacement

This 2015 campaign concluded a partial mooring replacement for ML 1, 2, 4, 8, 9, 10, 11 and 12 as well as a complete mooring replacement for ML 3. The project scope of the Phase 2 mooring replacement consisted of the following:

  • Installation of two new anchors utilizing a reaction anchor for tensioning;
  • Inspection of specified mooring components;
  • Change out of most, if not all, components for a full replacement of two of the mooring lines;
  • Change out of specified components for a partial replacement of seven of the mooring lines;
  • Removal of samples for forensic analysis.

Related projects

Selected filters

Installation gas pipeline, Balgzand-Bacton

BBL Company was established to design, construct, operate and exploit the Balgzand-Bacton Pipeline (BBL) for the transmission of natural gas from Balgzand, the Netherlands to Bacton in the United Kingdom. The overall length of the 36" offshore pipeline is some 230 kilometers. The capacity is around 42 million m3 of gas a day. As part of the pipeline installation, Saipem UK Ltd awarded Boskalis Offshore the contracts for the shore approaches at Julianadorp, the Netherlands and Bacton in the United Kingdom and the presweeping and rock dumping works along the pipeline route on the North Sea.

Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.