To main content

Onshore co-mining project, Lelydorp

Suralco L.L.C., an indirect joint subsidiary of Alcoa Inc. and Alumina Ltd., has awarded Boskalis a contract for the mining of bauxite in Lelydorp, Suriname. Boskalis is responsible for the entire mining process, from engineering and overburden removal to bauxite mining and ore delivery.

Mobilization

One of the most challenging operations of the project involved moving the Boskalis cutter suction dredger Orion from Abu Dhabi to the heart of the Surinam jungle. Overcoming bad weather and numerous engineering challenges, Boskalis managed to complete this job safely.

Wet overburden stripping

The Orion removed the wet overburden – consisting of both soft and stiff clays – prior to the mining operations.

Dry overburden stripping and mining

When the dredging has finished, the remaining overburden will be removed by our dry earth movement fleet, which consists of hydraulic excavators, articulated dump trucks and auxiliary equipment. Our earthmoving expertise means we will execute the entire production process from pit to plant. This includes activities such as fine stripping, ore sampling, drilling & blasting, ore haulage and ROM pad management.

Engineering and surveying

The wet overburden removal is charted using hydrographic single beam measurements; the dry excavation of overburden and mining progress is meticulously monitored by state of the art techniques such as UAV-photogrammetric and laser-scanning surveys.

Related projects

Selected filters
DSC03484_header.jpg

Cleanup, Westergasfabriek

The Westergasfabriek was built by the British firm Imperial Continental Gas Association (ICGA) in 1883, and was at the time the biggest coal-fired gas factory in Amsterdam. The project site, covering four hectares, housed coal storage yards, gasometers, purification plants, a water tower and office buildings, all designed by the famous Dutch architect Isaac Gosschalk. The municipal energy company used the site for storage into the early 1990s.

Bahrain_header.jpg

Land reclamation, Shaikh Khalifa Bin Salman Causeway

The Shaikh Khalifa Bin Salman Causeway is located in the State of Bahrain in an expanse of water called the Khawr Al Qulayah. It connects the Hidd Drydock Highway to the Mina Sulman Port. This major infrastructure project is carried out in advance of the planned expansion of the Bahrain port activities. This New Port project is planned at the Hidd side and via the Shaikh Khalifa Bin Salman Causeway direct connected with the existing Mina Sulman port and Saudi Arabia. The total length of the Shaikh Khalifa Bin Salman Causeway is approximately 6,500 m, including a bridge of 400 m, which was constructed in 2000.

Oresund.jpg

Tunnel construction Øresund, Denmark - Sweden

The Øresund Tunnel forms part of the Øresund Link that connects the cities of Copenhagen in Denmark and Malmö in Sweden across the Øresund.

Chek_Lap_Kok__09-06-1995.jpg

Land reclamation Check Lap Kok airport Hong Kong

In 1996 Hong Kong was a modern city-state with almost 6 million inhabitants where air traffic was a very important component for economic activity. The old airport Kai Tak, with a single runway, was no longer able to cope with the growing number of passengers and amount of freight.  The authorities decided to build a new, bigger airport at a new location in Hong Kong, a 350 hectares hilly island off the coast about 28 km west of the city center.