To main content

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

The oldest Maersk Oil field, Dan Bravo, is located in the Danish sector of the North Sea. The first platform in the complex was installed in 1972. The complex consists of platforms A, B, C and D. The Dan B platform forms the production hub of the Dan Bravo Complex and Dan A platform is one of the wellhead platforms at the Dan Bravo complex. Maersk Oil decided to carry out a platform lifetime extension program for the forty year old jacket structure to extend the service period of the structure until 2042.

General summary of the work scope

  • Reduce sea wave load unto the jacket structure by removing old boat fenders and pump caissons.
  • Inspection history enhancement by investigating all available inspection data, searching for known cracks in the subsea structure and inspecting potential problem areas.
  • Remove crack or damaged areas and replace with new structure (e.g. conductor guide level).
  • Reinforce subsea structure by adding retrofit (clamped) structures to strengthen key areas.
  • Renew consumables by retrofitting additional anodes by means of clamps due to depletion and removing some of the original anodes.
The 2013 offshore campaign started in July and was completed in September. During this campaign Boskalis performed the 3D subsea photogrammetry activities, classified as world’s largest ever undertaken, by air/saturation diving and ROV operations acquiring exact geometrical information of subsea K-joints to be able to design reinforcement clamps. Operations were performed on depths varying from 10 to 41 meters. Besides the technical challenges the environmental conditions as sea-state, fog and subsea reduced visibility (minimum 2 meter required for image taking) dictated the progress of the work.

Related projects

Selected filters

Gas pipeline project, Trans Thailand Malaysia

The Trans Thailand Malaysia Gas Pipeline Project comprised the installation of a 34 inch concrete coated gas pipeline, running from the joint Thai-Malaysia development area approximately 270 kilometers offshore towards the southern Thai coast near Chana. As part of this project a contract was awarded to the Boskalis Offshore B.V. - Tideway B.V. consortium for the provision of the dredging and backfilling works, whereas Boskalis Offshore provided the main equipment and project support.

Seahorse_04_header.jpg

Glory hole excavation, White Rose

The White Rose offshore oil field is the third major oil field in the Jeanne d’Arc Basin on the Grand Banks, some 350 kilometers east of St. John’s, Newfoundland, Canada and within 50 kilometers from the Terra Nova and Hibernia fields. The South White Rose oil pool covers approximately 40 square kilometers and contains an estimated 200-250 million barrels of recoverable oil.

Development gas export pipeline,
Hibiscus to Point Fortin

The NCMA Development Project comprised the development of the North Coast Marine Area, which is located in the Caribbean Sea and Bay of Paria, Trinidad. The project included the installation of a 24" Gas Export Pipeline from the Hibiscus Platform to a landfall at Point Fortin. From the landfall the pipeline was routed by directional drilling and by surface laid pipeline, to a termination point in the Atlantic LNG Terminal at Point Fortin. As part of this project Boskalis was awarded the contract for the provision of landfall, directional drilling and onshore pipeline installation and testing of the 24" gas pipeline system.

Sandpiper_foto_offshore_2_header.jpg

Hanze F2a Development Project

Hanze, 200 kilometers offshore Den Helder in block F/2 of the North Sea, is the first operated development in the Dutch sector by Germany's Veba Oil. The oilfield reserved approximate 34 million bbl, plus 40 bcf of associated gas. 

Installation gas pipeline, Takoradi

Late November 1998 Boskalis was awarded a subcontract for the installation of two marine pipelines to supply and discharge cooling seawater for the Takoradi thermal power plant that was under construction for the Volta River Authority, near the village of Aboadze approximately 20 kilometers north-east of Takoradi, Republic of Ghana.

WD_Fairway_and_Sandpiper_near_platform_header.jpg

Re-insulation Gannet 'C' Bundles, North Sea

The Gannet 'C' satellite field, which is located in the North Sea at 112 miles East of Aberdeen in 95-meter water depth, comprises four drill centres, each having one or more producing wells. The drill centres are connected to the local platform Gannet 'A' by four flowline bundles with a total length of 10 kilometers. A glycol-based gel, filling the annulus of the Gannet 'C' carrier pipe, insulated the individual flow lines. Prompted by degradation of the gel and the resulting drop in oil and gas arrival temperatures at the platform, an EPIC project took off for a re-insulation system. The objective of the re-insulation system was that it should provide sufficient insulation to the bundles in order to safeguard production during the total field life of Gannet 'C', being a minimum lifetime of 15 years. Boskalis Offshore was supported by Hydronamic - the in-house engineering department.