To main content

Port and MOF, LNG plant Barrow Island, Gorgon

Design and construction of a new port and materials offloading facility in a class 'A' nature reserve. The project owner is developing LNG process facilities on Barrow Island off the north west coast of Western Australia approximately 140 km west of Dampier and 95 km north east of Onslow. Barrow Island is a Class A Nature Reserve and an internationally important conservation estate.

Scope of work

Boskalis’ scope of work on the project included:
  • Detailed design and construction of a Pioneer Materials Offloading Facility (PMOF).
  • Design and construction of abutment structures for a Ro-Ro berth, module carrier berth and barge berth.
  • Design and construction of mooring dolphins and access walkways for the PMOF barge berth, module carrier berth and Ro-Ro berth.
  • Dredging and reclamation work for the approach channel, turning basin and berth pockets associated with the construction of the MOF.
  • Dredging for the LNG jetty area including an approach channel, turning basin and berth pockets.
  • Installation of temporary and permanent navigation aids including two permanent front and rear lead support structures.
  • Provision and operation of a Marine Construction Support Vessel to accommodate personnel involved in the Project.
  • Construction of the Eastern Materials Offloading Facility (EMOF) causeway including all armour rock, construction of a breakwater, placement of X-blocs and installation of concrete nib wall.
  • Compaction of the EMOF (Cofra).
  • Materials testing (Boskalis Environmental).

Dredging and reclamation works

The dredging works consisted of 2 major parts:
  • A MOF access channel and turning basin to create access for heavy load transport vessels to bring in construction materials and large modules for the construction of the LNG plant on Barrow Island.
  • An access channel and turning basin for the LNG carriers once the plant is operational.

Rock protection and breakwater works

These works consisted of 3 major components:
  • Design and construction of a protection of the MOF platform against cyclonic waves with rock only.
  • Construction of a protection of the EMOF platform against cyclonic waves with rock underlayers and concrete X-blocs.
  • Construction of a breakwater for protection of a tug harbour against cyclonic waves with rock underlayers and concrete X-blocs.

Related projects

Selected filters
2005-09-16-124619-9920_header.jpg

Dredging of sediments, Miami river

The Miami River, which flows through an urban industrial area of Miami, Florida, had not been dredged since the area was built in 1934. In 1990 the US Army Corps of Engineers advised the city that the sediment had to be removed from the river as it was impeding shipping. There was one caveat however: the sediment, contaminated with heavy metals, pesticides and oil, could not be placed in the ocean.

klein_1_header.jpg

Gas fields development, Krishna Godavari basin

A large-scale dredging, trenching, pipe pulling and backfilling project. Reliance Industries develops the offshore gas field known as Block KGDWN-98/3 in the Krishna Godavari Basin, Bay of Bengal off the East Coast of India. The gas field will be linked to onshore customers and covers an area of approximately 7,500 km2. The field stretches an area 40 to 60 kilometers southeast of Kakinada. The scope of works comprised the dredging of a 21 kilometers long and 18 meters wide trench for three 24" gas pipelines, each with a 6" piggyback pipeline, one 12" effluent pipeline and two umbilical cables in water depths ranging from 0 to 50 meters. After pipe laying by the main contractor the pipeline trench was backfilled with partly rock and sand.

Rehabilitation of old breakwater, Port of Poti

The city of Poti is located at the mouth of Georgia’s largest river, the Rioni. It has been an important trade centre for centuries. Since the early 19th century, many plans have been developed for the creation of a major sea port. Construction work started in the 1850s on the main breakwater that is still protecting the port today. During its long lifetime, this structure has been maintained by frequently adding 20-60 tons of concrete cubes to the armour layer. Significant settlement of the structure over time has lowered the crest level considerably, resulting in large overtopping volumes and therefore in port-operation downtime. As a result, a rehabilitation project was executed between 2006 and 2008 by Royal Boskalis Westminster N.V. to reduce the downtime caused by overtopping waves.

Sepetiba_aerial_header.jpg

Reclamation and dewatering works, Sepetiba Bay

The German steel-maker ThyssenKrupp Steel and the Brazilian mining giant Companhia Vale do Rio Doce (CVRD) teamed up to construct a EUR 3 billion steel factory at Sepetiba. This is a small town of 36,000 inhabitants near Rio de Janeiro with good access to the Atlantic Ocean. The new steel factory allowed Brazil not only to export more of its plentiful mineral resources, but also to produce semi-finished products that can be sold at higher margins. The government authorities of Brazil and Rio de Janeiro both supported the project.

SBS_Reclamation_23-05-08_60_header.jpg

Port development, Lerwick

The Port of Lerwick is situated on the east coast of the Shetland Islands, and is operated by Lerwick Port Authority. The 2008 dredging and reclamation works were one of the largest marine projects to be carried out in Scotland in recent years and constituted the largest single investment in the port to date.

vuosaari_1_header.jpg

Port construction, Vuosaari

Vuosaari Harbor is the most significant harbor project in Finnish history; in fact, it is unique even on a European scale. Both existing harbors in Helsinki’s city centre are being transferred to the eastern outskirts of the city. They are being replaced with a harbor with excellent traffic connections that can meet the increasing demand for cargo handling. The Vuosaari Harbor Center will provide a competitive and modern service package, with smooth connections between harbor operations and other logistical facilities. The harbor center will comprise the gate area, the closed harbor area and the adjacent Business Parks. The fairway to the Harbor Center will be 32 km long, at least 200 m wide, and 11 m deep. The port area comprises 150 ha, of which 90 ha will be land reclaimed from the sea.