Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

In anticipation of offshore wind farm developments in France, the Port Authorities of Cherbourg and Caen-Ouistreham have decided to expand their ports to accommodate this industry.

Project specifications

A specific contract requirement for the quay wall and terminal was the bearing capacity of 15 t/m2 and the maximum allowed settlement of 3 cm under a load of 15 t/m2. Two berth pockets were constructed at the same time: one with a water depth of 14 m and the other with a depth of 10 m. A turning circle in front of the new quay was dredged to a depth of -12 m. In the joint venture, Soletanche-Bachy was responsible for all the civil-engineering work and Atlantique Dragage was in charge of the marine work. The execution of the project was divided in four stages:

  • Dredging of turning circle and both berth pockets. The dredged materials were designated for the construction of a temporary bund, needed to build the diaphragm walls (quay wall and anchor wall);
  • Construction of the quay wall;
  • Removal of the temporary bund on the outside of the new quay wall. The dredged materials to be used for the reclamation of a new terminal behind the constructed quay;
  • Testing and hand-over of the work.

Related projects

Selected filters
hfd_onder_header.jpg

Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

Balboa_2_header.jpg

Port expansion, Balboa

The plans to expand the Panama Canal represent one of the most important infrastructure improvements of the 21st century. Since its opening in 1913 the Canal has provided the shortest and most economically viable shipping route from Pacific to Atlantic seaports. With the ever-increasing size of modern-day vessels, it was inevitable that the Canal would need to be widened and deepened. The expansion of the Canal has made the extension of the Port of Balboa at the mouth of the canal on the Pacific Ocean a necessity. The Phase 4 projects included Marine Works and Civil Works to improve two existing berths and to build a completely new berth capable of handling not only Post Panamax but also Super Post Panamax ships.

DSCF0226_header.jpg

Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

Figure_1_header.jpg

Port environmental mitigation measures, Hamina

Hamina, which is close to the Russian border in south-east Finland, is a home port for the oil industry and a transit harbor for timber, cars and other goods on their way to Russia. To provide access for larger vessels it had to deepen the existing channel by two meters to 12 meters and create a new channel section. Terramare Oy, a subsidiary of Royal Boskalis Westminster, won this assignment in late 2008. The project started in July 2009.

Raahe_1_header.jpg

Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.

_L4F8705_header.jpg

Port development, Pipavav

As a result of the booming container market in recent years, GPPL and APM Terminals introduced a long term investment plan to further develop the port’s facilities. Phase 2 of the expansion program included the reclamation of a new storage (container stacking) area and the extension of the port’s capacity by deepening the approach, channels and berths, allowing larger (container) vessels to enter the port. Zinkcon Marine Singapore, a subsidiary of Boskalis International B.V., won the contract for the dredging and reclamation works for Phase 2. In the beginning of 2009, however, the client re-evaluated the investment against the background of the dramatic effects of the economic crisis, which seriously affected the global container market. GPPL, APMT and ZMS agreed to optimize the project in such a way that all parties would benefit.