Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

In anticipation of offshore wind farm developments in France, the Port Authorities of Cherbourg and Caen-Ouistreham have decided to expand their ports to accommodate this industry.

Project specifications

A specific contract requirement for the quay wall and terminal was the bearing capacity of 15 t/m2 and the maximum allowed settlement of 3 cm under a load of 15 t/m2. Two berth pockets were constructed at the same time: one with a water depth of 14 m and the other with a depth of 10 m. A turning circle in front of the new quay was dredged to a depth of -12 m. In the joint venture, Soletanche-Bachy was responsible for all the civil-engineering work and Atlantique Dragage was in charge of the marine work. The execution of the project was divided in four stages:

  • Dredging of turning circle and both berth pockets. The dredged materials were designated for the construction of a temporary bund, needed to build the diaphragm walls (quay wall and anchor wall);
  • Construction of the quay wall;
  • Removal of the temporary bund on the outside of the new quay wall. The dredged materials to be used for the reclamation of a new terminal behind the constructed quay;
  • Testing and hand-over of the work.

Related projects

Selected filters
hires-6917.jpg

Construction motorway, A4 Delft-Schiedam

Boskalis Nederland was involved in the construction of the A4 motorway from Delft to Schiedam. The client is Rijkswaterstaat. After 40 years, the construction of this final section will bring to an end the public debate about whether this new road was needed.

Boskalis_Suezkanaal_cutter_suction_dredgers_4153_header.jpg

Channel expansion, Suez

The Suez Canal is one of the world’s main shipping links and thus of major importance to world trade. The canal extends from Suez on the Red Sea to Port Said on the Mediterranean. Egypt’s Suez Canal Authority awarded the contract to double the canal’s capacity to a consortium, which was aptly named the Challenge Consortium by the Chairman of the Suez Canal Authority, Admiral Mohab Mamish.

DSC_0008_header.jpg

Onshore co-mining project, Lelydorp

Suralco L.L.C., an indirect joint subsidiary of Alcoa Inc. and Alumina Ltd., has awarded Boskalis a contract for the mining of bauxite in Lelydorp, Suriname. Boskalis is responsible for the entire mining process, from engineering and overburden removal to bauxite mining and ore delivery.

Picture_6_header.jpg

Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

P1030713_header.jpg

Dredging and reclamation, Songdo International City

Boskalis has been awarded a contract by Daewoo E&C for the dredging and reclamation of new land for Songdo International City on the waterfront of Incheon, South Korea. The total value of the contract amounts to approximately EUR 80 million.

CIMG1866_header.jpg

Coastline fixation, Cotonou

The project was developed to arrest coastline erosion in the densely-populated centre of Cotonou caused by two phenomena: erosion and human interference along the West African coastline.