Port development, Cherbourg

To accommodate an assembly plant for wind turbines, a 220 m quay wall had to be added to the existing quay and two hectares of land behind the new quay had to be reclaimed.

In anticipation of offshore wind farm developments in France, the Port Authorities of Cherbourg and Caen-Ouistreham have decided to expand their ports to accommodate this industry.

Project specifications

A specific contract requirement for the quay wall and terminal was the bearing capacity of 15 t/m2 and the maximum allowed settlement of 3 cm under a load of 15 t/m2. Two berth pockets were constructed at the same time: one with a water depth of 14 m and the other with a depth of 10 m. A turning circle in front of the new quay was dredged to a depth of -12 m. In the joint venture, Soletanche-Bachy was responsible for all the civil-engineering work and Atlantique Dragage was in charge of the marine work. The execution of the project was divided in four stages:

  • Dredging of turning circle and both berth pockets. The dredged materials were designated for the construction of a temporary bund, needed to build the diaphragm walls (quay wall and anchor wall);
  • Construction of the quay wall;
  • Removal of the temporary bund on the outside of the new quay wall. The dredged materials to be used for the reclamation of a new terminal behind the constructed quay;
  • Testing and hand-over of the work.

Related projects

Selected filters
FF66817_header.jpg

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Cornelis_Zanen.jpg

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Gabon_Libreville1920.jpg

Port development,
Libreville - Gabon

A new area was constructed in the Port of Libreville for a mineral terminal, dry dock, fishing port, processing facilities and other port activities, such as aggregate processing. This new port development was required to improve and strengthen the logistic capacity for the inland mining industry, to reduce export costs, and thus to increase the competitiveness of mineral exports from Gabon.

Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

IMG_3549_header.jpg

Cleanup sediment treatment, Fox river

As a result of industrialization the riverbed of the Fox River (Wisconsin, USA) had become contaminated with PCBs (polychlorinated biphenyls). Joining together a number of large paper mills based on the banks of the river have established the Fox River Cleanup Group to handle the remediation project. The site is on the federal Superfund program’s National Priorities List.

Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.