Port development, Mombasa

The Port of Mombasa is currently the biggest port on the coast of East Africa north of Durban, and the only international port in Kenya. It is now in the throes of a huge expansion drive to both increase cargo handling capacity and accommodate Panamax and Post Panamax vessels. The port is a transit route for, mainly, Uganda, Rwanda, South Sudan and Northern Tanzania. The current container terminal has an installed capacity of 250,000 TEU but handled more than 770,000 TEU in 2011. The port will raise its profile as a regional hub by building a second container terminal with a capacity of 1.2 million TEU. The port authority decided to construct the container terminal in phases.

Challenges

The main challenge on the project was the fact that Boskalis had to work with weak subsoil with a low bearing capacity. There were also environmental challenges because the sand borrow area was situated between marine reserve parks.

Work method

On 1 August 2012, Boskalis International B.V. signed the sub-contract for the dredging and reclamation works for the first construction phase for the second container terminal. Before construction of the quay walls, three deep trenches were dredged by TSHDs Argonaut and Willem van Oranje to remove the weak subsoil and replace it with sand. Boskalis soil specialists invested large amounts of time and energy in sourcing suitable sand in the immediate vicinity of the project. After the removal of 1 million m3 of soil, the soil improvement area was filled with offshore sand by TSHD Willem van Oranje and a spray pontoon. Reclamation had to take place very carefully to avoid mud slides and circular slip. During reclamation to +1 m CD, the spray pontoon SP10, positioned on six anchors, was used to apply layers of 75 cm; that part of the work was completed successfully on 11 March 2013. The remaining sand was applied in layers up to +5.5 m CD using land pipelines. Boskalis successfully met some challenges with extreme local settlements. The +5,5 m CD level was completed on 7 May 2013. This activity was followed by a surcharge fill to a maximum of +11 m CD to reduce settlement time.

Related projects

Selected filters
DJI_0005__4_.JPG

Construction of greenfield port and breakwater for Dangote quays Lekki

The Dangote Group, owned by Aliko Dangote, is building Africa’s largest oil refinery and fertilizer plant in Lekki, 60 kilometers east of Lagos, Nigeria. To facilitate the import of out-of-gauge components and other materials required for construction activities, a port was constructed

P67.jpg

P67 FPSO Transportation

On behalf of Company Petrobras and Client COOEC, Boskalis executed the dry transportation of the P-67 FPSO in 2018 from the COOEC Qingdao yard in China to Rio de Janeiro in Brazil. The P-67 FPSO will produce 150,000 bpd and compress six million cubic meters of natural gas daily in the Lula North section of the Lula-Cernambi field in the Santos basin.

Harderwijk_Lorentzhaven__7__header.jpg

Redevelopment Waterfront, Harderwijk

Boskalis Nederland is involved in one of the largest redevelopment projects in the Netherlands. The Harderwijk Waterfront project involves the complete transformation of the lakeside area of this IJsselmeer town. The project covers a strip approximately six kilometers long, combining homes, work and recreation in a natural way. The Harderwijk Waterfront will generate a quality boost in many areas: quality of life, employment, traffic, tourism and the environment.

Pluit_City_Island-bird_eye_view.jpg

Artificial island
off the coast of
Jakarta, Indonesia

Boskalis has been awarded a contract by PT Muara Wisesa Samudra to design and construct an artificial island measuring 160 hectares off the coast of Jakarta, Indonesia. The work is part of the dredging and land development works for the new Pluit City. It will be executed in a joint venture with Van Oord.

Medium-Foto_1_-_artist_impression_nw_situatie_A1_afslag_met_spoorbrug__1_.jpg

Road enlargement motorway A1-A6, Diemen-Almere

The A1/A6 project is one of the five sub-projects for Rijkswaterstaat that are included in the upgrading of the road network linking Schiphol Airport, Amsterdam, and Almere (SAA). The total length of the SAA link is 40 kilometers. Boskalis, together with partners, is responsible for the section from the Diemen intersection to Almere, a distance of approximately 23 kilometers.

29-8-11_006_header.jpg

Port maintenance,
Açu Port

Açu Port in São João da Barra, Rio de Janeiro (Brazil) is one of the largest port-industry complex in Latin America. The port consists of two terminals: T1, an offshore terminal for handling iron ore and oil, and T2, an onshore terminal built around the inner navigation channel which accommodates offshore supply companies and will handle bauxite, general cargo and vehicles.