The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Scope of work

This first phase of the project required the construction of an access channel and the deepening of a lagoon to create part of a turning basin. Due to two existing bridges it was required that the dredging equipment was mobilized to Cuyutlan on top of pontoons so it could be offloaded onto the shore and  transported over land for several hundreds of meters and launched into the lagoon before the dredging operations could commence. This port expansion project was driven by a need to cater to larger vessels and future trade volumes. This Liquefied Natural Gas (LNG) project emphasizes the need for infrastructure to accommodate strong demand for energy resources. The second and final phase of the dredging work required further dredging in the lagoon and at the outer part of the access channel. The work includes the deepening of the basin, the construction of an access channel and the creation of a turning basin. Boskalis has a strong home market position in Mexico and the majority of the Boskalis work was executed by our own local employees.

Design and execution

During the execution of the project the scope of the work shifted continuously. As a consequence access to the site was held up by delays in the work of other parties. The client extended the contract duration and it was therefore still possible to deliver the project on time. Most of the engineering was done by third parties, with Hydronamic (the Boskalis engineering consultancy) playing a supporting role. The most significant changes in the scope of work, such as the clearance of old breakwaters of  175,000 m3, were solved by Hydronamic.

Related projects

Selected filters
Marker_Wadden_spread_def_1920.jpg

Construction of
Marker Wadden

Boskalis has been awarded the first phase of the Marker Wadden development in the Netherlands. The project includes the construction of an island with underwater landscaping. The Marker Wadden are natural islands that will be developed in the Markermeer lake in the years to come. They will provide a major boost for the ecological quality of the Markermeer lake. The natural shores of the islands will give fish more opportunities to spawn and feed. As a result, large numbers of birds such as terns and waders will return to the area because there will be more food for them. The construction of the Marker Wadden will transform the map of the Netherlands.

Adelaide.png

Outer harbor channel widening, Adelaide.

The Port of Adelaide is the primary port in South Australia, located at Outer Harbor. The port is operated by Flinders Ports Pty Ltd (Flinders Ports) and handles both container and cruise vessels, contributing significantly to the State’s economic activity. Flinders Ports identified the need for an upgrade of the existing infrastructure driven by the emergence of Post Panamax class vessels. To meet this growth the existing channel had to be widened to accommodate vessels with a maximum width of 49 m without operational restrictions. Flinders Ports contracted Boskalis to execute the dredging works.

Medium-FF95893.jpg

Johan Sverdrup, transport.

Samsung Heavy Industries Co., Ltd. is Equinor’s Fabrication and Transport contractor of the Johan Sverdrup project. Boskalis has been awarded by Samsung as transportation contractor for this project.

DSC_0204_header.jpg

IJsseldelta

The IJsseldelta project is part of the national Room for the River program, which comprises over 30 measures aimed at upgrading the flood defenses in the Dutch river areas. The project involves lowering the summer bed of the Lower IJssel river along a length of 7.5 kilometers near the town of Kampen and creating a bypass to the south of Kampen.

Port expansion, Tuas Mega Port Singapore

Boskalis is part of a consortium that won a contract related to the construction of the Tuas Mega Port in Singapore. After Shanghai, Singapore is not only the world's largest container port, it also handles 50% of global crude oil production and it is the planet's busiest transit port. The port is the economic motor of Singapore, which is constantly struggling with a shortage of land.

DJI_0005__4_.JPG

Construction of greenfield port and breakwater for Dangote quays Lekki

The Dangote Group, owned by Aliko Dangote, is building Africa’s largest oil refinery and fertilizer plant in Lekki, 60 kilometers east of Lagos, Nigeria. To facilitate the import of out-of-gauge components and other materials required for construction activities, a port was constructed